11 research outputs found
Optimization of the powering tests of the LHC superconducting circuits
The Large Hadron Collider has (LHC) 1572 superconducting circuits which are distributed along the eight 3.5 km LHC sectors [1]. Time and resources during the commissioning of the LHC technical systems were mostly consumed by the powering tests of each circuit. The tests consisted in carrying out several powering cycles at different current levels for each superconducting circuit. The Hardware Commissioning Coordination was in charge of planning, following up and piloting the execution of the test program. The first powering test campaign was carried out in summer 2007 for sector 7-8 with an expected duration of 12 weeks. The experience gained during these tests was used by the commissioning team for minimising the duration of the following powering campaigns to comply with the stringent LHC project deadlines. Improvements concerned several areas: strategy, procedures, control tools, automatization, and resource allocation led to an average daily test rate increase from 25 to 200 tests per day. This paper describes these improvements and details their impact on the operation during the last months of LHC Hardware Commissioning
Performance of the Superconducting Corrector Magnet Circuits during the Commissioning of the LHC
The LHC is a complex machine requiring more than 7400 superconducting corrector magnets distributed along a circumference of 26.7 km. These magnets are powered in 1446 different electrical circuits at currents ranging from 60Â A up to 600 A. Among the corrector circuits the 600 A corrector magnets form the most diverse and differentiated group. All together, about 60000 high current connections had to be made. A fault in a circuit or one of the superconducting connections would have severe consequences for the accelerator operation. All magnets are wound from various types of Nb-Ti superconducting strands, and many contain parallel protection resistors to by-pass the current still flowing in the other magnets of the same circuit when they quench. In this paper the performance of these magnet circuits is presented, focussing on the quench behaviour of the magnets. Quench detection and the performance of the electrical interconnects will be dealt with. The results as measured on the entire circuits are compared to the test results obtained at the reception of the individual magnets
Performance of the Main Dipole Magnet Circuits of the LHC during Commissioning
During hardware commissioning of the Large Hadron Collider (LHC), 8 main dipole circuits are tested at 1.9 K and up to their nominal current. Each dipole circuit contains 154 magnets of 15 m length, and has a total stored energy of up to 1.3 GJ. All magnets are wound from Nb-Ti superconducting Rutherford cables, and contain heaters to quickly force the transition to the normal conducting state in case of a quench, and hence reduce the hot spot temperature. In this paper the performance of the first three of these circuits is presented, focussing on quench detection, heater performance, operation of the cold bypass diodes, and magnet-to-magnet quench propagation. The results as measured on the entire circuits will be compared to the test results obtained during the reception tests of the individual magnets
Coordination of the commissioning of the LHC technical systems
The Large Hadron Collider operation relies on 1232 superconducting dipoles with a field of 8.33T and 400 superconducting quadrupoles with a strength of 220 T/m powered at 12kA, operating in superfluid He at 1.9K. For dipoles and quadrupoles as well as for many other magnets more than 1700 power converters are necessary to feed the superconducting circuits. A sophisticated magnet protection system is crucial to detect a quench and safely extract the energy stored in the circuits (about 1GJ only in one of the dipole circuits) after a resistive transition. Besides, in such complex architecture, many technical services (e.g. cooling and ventilation, technical network, electrical distribution, GSM network, controls system, etc.) have to be reliably available during commissioning. Consequently, the commissioning of the technical systems and the associated infrastructures has been carefully studied. Procedures, automatic control and analysis tools, repositories for test data, management structures for carrying out and following up the tests have been put in place. This paper briefly describes the management structure and tool created to ensure safe, smooth and rapid commissioning
Scheduling the powering tests
The Large Hadron Collider is now entering in its final phase before receiving beam, and the activities at CERN between 2007 and 2008 have shifted from installation work to the commissioning of the technical systems ("hardware commissioning"). Due to the unprecedented complexity of this machine, all the systems are or will be tested as far as possible before the cool-down starts. Systems are firstly tested individually before being globally tested together. The architecture of LHC, which is partitioned into eight cryogenically and electrically independent sectors, allows the commissioning on a sector by sector basis. When a sector reaches nominal cryogenic conditions, commissioning of the magnet powering system to nominal current for all magnets can be performed. This paper briefly describes the different activities to be performed during the powering tests of the superconducting magnet system and presents the scheduling issues raised by co-activities as well as the management of resources
Short Circuit Tests: First Step of LHC Hardware Commissioning Completion
For the two counter rotating beams in the Large Hadron Collider (LHC) about 8000 magnets (main dipole and quadrupole magnets, corrector magnets, separation dipoles, matching section quadrupoles etc.) are powered in about 1500 superconducting electrical circuits. The magnets are powered by power converters that have been designed for the LHC with a current between 60 and 13000A. Between October 2005 and September 2007 the so-called Short Circuit Tests were carried-out in 15 underground zones where the power converters of the superconducting circuits are placed. The tests aimed to qualify the normal conducting equipments of the circuits such as power converters and normal conducting high current cables. The correct operation of interlock and energy extraction systems was validated. The infrastructure systems including AC distribution, water and air cooling and the control systems was also commissioned. In this paper the results of the two year test campaign are summarized with particular attention to problems encountered and how they were solved
The Commissioning of the LHC Technical Systems
The LHC is an accelerator with unprecedented complexity where the energy stored in magnets and the beams exceeds other accelerators by one-to-two orders of magnitude. To ensure a safe and efficient machine start-up without being plagued by technical problems, a phase of "hardware commissioning" was introduced: a thorough commissioning of technical systems without beam. This activity started in June 2005 with the commissioning of individual systems, followed by operating a full sector, one eighth of the machine; the commissioning is expected to last until spring 2008 when commissioning with beam will start. The LHC architecture allows the commissioning of each of the eight sectors independently from the others, before the installation of other sectors is complete. An important effort went into the definition of the programme and the organization of the coordination in the field, as well as in the preparation of the tools to record and analyze test results. This paper discusses the experience with this approach, presents results from the commissioning of the first LHC sector and gives an outlook for future activities
Genomic-based breeding for climate-smart peach varieties
Improving the performance of peach varieties in the context of climate change requires multiple approaches. Not only will climate change alter plant phenology, but it will also drive negative effects of several biotic and abiotic stressors. The challenge is to improve adaptation of varieties to a changing environment, while maintaining organoleptic qualities of the fruit. This chapter focuses on the progress in genomics-assisted breeding in peach to break barriers in conventional breeding. Breeding climate-smart (CS) peach trees requires the identification of CS traits used in the adaptation to high levels of temperature, CO2, water deprivation and biotic stress. Relevant CS traits, such as those that control flowering time (chilling and heat requirements), biotic and abiotic stress tolerance (pests and diseases; water-nutrient efficiency), require prioritization. Here, we review classical mapping and breeding of peach varieties, the progress and limitations of the used of marker-assisted selection and breeding (MAS and MAB, respectively) in expression of traits, such as fruit quality and stress tolerance, and describe the rationale for the use of molecular breeding.EEA San PedroFil: Gogorcena Aoiz, Yolanda. Consejo Superior de Investigaciones Científicas (CSIC). Estación Experimental Aula Dei; EspañaFil: Sánchez, Gerardo. Instituto Nacional de Tecnología Agropecuaria (INTA). Estación Experimental Agropecuaria San Pedro; ArgentinaFil: Moreno-Vázquez Santiago. Universidad Politécnica de Madrid. Escuela Técnica Superior de Ingeniería Agronómica, Alimentaria y de Biosistemas; EspañaFil: Pérez, Salvador. Centro de Recursos Geneticos y Mejoramiento de Prunus; MéxicoFil: Ksouri, Najla. Consejo Superior de Investigaciones Científicas (CSIC). Estación Experimental Aula Dei; Españ
Characterisation of microbial attack on archaeological bone
As part of an EU funded project to investigate the factors influencing bone preservation in the archaeological record, more than 250 bones from 41 archaeological sites in five countries spanning four climatic regions were studied for diagenetic alteration. Sites were selected to cover a range of environmental conditions and archaeological contexts. Microscopic and physical (mercury intrusion porosimetry) analyses of these bones revealed that the majority (68%) had suffered microbial attack. Furthermore, significant differences were found between animal and human bone in both the state of preservation and the type of microbial attack present. These differences in preservation might result from differences in early taphonomy of the bones. © 2003 Elsevier Science Ltd. All rights reserved