146 research outputs found

    Client-contractor bargaining on net present value in project scheduling with limited resources

    Get PDF
    The client-contractor bargaining problem addressed here is in the context of a multi-mode resource constrained project scheduling problem with discounted cash flows, which is formulated as a progress payments model. In this model, the contractor receives payments from the client at predetermined regular time intervals. The last payment is paid at the first predetermined payment point right after project completion. The second payment model considered in this paper is the one with payments at activity completions. The project is represented on an Activity-on-Node (AON) project network. Activity durations are assumed to be deterministic. The project duration is bounded from above by a deadline imposed by the client, which constitutes a hard constraint. The bargaining objective is to maximize the bargaining objective function comprised of the objectives of both the client and the contractor. The bargaining objective function is expected to reflect the two-party nature of the problem environment and seeks a compromise between the client and the contractor. The bargaining power concept is introduced into the problem by the bargaining power weights used in the bargaining objective function. Simulated annealing algorithm and genetic algorithm approaches are proposed as solution procedures. The proposed solution methods are tested with respect to solution quality and solution times. Sensitivity analyses are conducted among different parameters used in the model, namely the profit margin, the discount rate, and the bargaining power weights

    Network decomposition-based benchmark results for the discrete time-cost tradeoff problem

    Get PDF
    In project management, the project duration can often be compressed by accelerating some of its activities at an additional expense. This is the so-called time–cost tradeoff problem which has been extensively studied in the past. However, the discrete version of the problem which is of great practical relevance, did not receive much attention so far. Given a set of modes (time–cost pairs) for each activity, the objective of the discrete time–cost tradeoff problem is to select a mode for each activity so that the total cost is minimized while meeting a given project deadline. The discrete time–cost tradeoff problem is a strongly -hard optimization problem for general activity networks. In terms of what current state-of-art algorithms can do, instances with (depending on the structure of the network and the number of processing alternatives per activity) no more than 20–50 activities can be solved to optimality in reasonable amount of time. Hence, heuristics must be employed to solve larger instances. To evaluate such heuristics, lower bounds are needed. This paper provides lower and upper bounds using column generation techniques based on “network decomposition”. Furthermore, a computational study is provided to demonstrate that the presented bounds are tight and that large and hard instances can be solved in short run-time

    Improved Lower Bounds for the Proportional Lot Sizing and Scheduling Problem

    No full text
    Where standard MIP--solvers fail to compute optimum objective function values for certain MIP--model formulations, lower bounds may be used as a point of reference for evaluating heuristics. In this paper, we compute lower bounds for the multi--level proportional lot sizing and scheduling problem with multiple machines (PLSP--MM). Four approaches are compared: Solving LP--relaxations of two different model formulations, solving a relaxed MIP--model formulation optimally, and solving a Lagrangean relaxation. Keywords: Multi--level lot sizing, scheduling, lower bounds, PLSP 1 Introduction The problem we are focussing at, can be described as follows: Several items are to be produced in order to meet some known (or estimated) dynamic demand without backlogs and stockouts. Precedence relations among these items define an acyclic gozinto--structure of the general type. In contrast to many authors who allow demand for end items only, now, demand may occur for all items including component ..

    Zum Problem der taktisch-operativen Entscheidung zwischen Eigen- oder Fremdfertigung

    No full text
    Summary in EnglishAvailable from Bibliothek des Instituts fuer Weltwirtschaft, ZBW, Duesternbrook Weg 120, D-24105 Kiel W 351 (374) / FIZ - Fachinformationszzentrum Karlsruhe / TIB - Technische InformationsbibliothekSIGLEDEGerman

    A genetic algorithm for multi-level, multi-machine lot sizing and scheduling

    No full text
    SIGLEAvailable from Bibliothek des Instituts fuer Weltwirtschaft, ZBW, Duesternbrook Weg 120, D-24105 Kiel W 351 (415) / FIZ - Fachinformationszzentrum Karlsruhe / TIB - Technische InformationsbibliothekDEGerman
    corecore