11 research outputs found
Recommended from our members
Duration and cost variability of construction activities: an empirical study
The unique nature of construction projects can mean that construction activities often suffer from duration and cost variability. Because this variability is unplanned, it can present a problem when attempting to complete a project on time and on budget. Various factors causing this variability have been identified in the literature, but they predominantly refer to the nature and/or context of the whole project rather than specific activities. In this paper, the order of magnitude of and correlation between activity duration and cost variability is analyzed in 101 construction projects with over 5,000 activities. To do this, the first four moments (mean, standard deviation, skewness, and kurtosis) of actual versus planned duration and cost (log) ratios are analyzed by project, phase of execution, and activity type. Results suggest that, contrary to common wisdom, construction activities do not end late on average. Instead, the large variability in the activity duration is the major factor causing significant project delays and cost overruns. The values of average activity duration and cost variability gathered in this study will also serve as a reference for construction managers to improve future construction planning and project simulation studies with more realistic data
Time Reduction for Completion of a Civil Engineering Construction Using Fuzzy Clustering Techniques
In the civil engineering field, there are usually unexpected troubles that can cause delays during execution. This situation involves numerous variables (resource number, execution time, costs, working area availability, etc.), mutually dependent, that complicate the definition of the problem analytical model and the related resolution. Consequently, the decision-maker may avoid rational methods to define the activities that could be conveniently modified, relying only on his personal experience or experts’ advices. In order to improve this kind of decision from an objective point of view, the authors analysed the operation correction using a data mining technique, called Fuzzy Clustering. This allows the analysts to represent complex real scenarios and classify the various activities according to their influence on the reduction of the total execution time. The proposed procedure provides positive results that are also in compliance with significant operational constraints, such as the control of costs and areas needed by the workers to perform the tasks. Finally, it is possible to increase the input variable number preserving the algorithm simplicity and avoiding lacks of accuracy in the final numerical outcomes
Recommended from our members
Do projects really end late? On the shortcomings of the classical scheduling techniques
Many engineering projects fail to meet their planned completion dates in real practice. This is a recurrent topic
in the project management literature, with poor planning and controlling practices frequently cited among the
most significant causes of delays. Unfortunately, hardly any attention has been paid to the fact that the classical
scheduling techniques—Gantt chart, Critical Path Method (CPM), and Program Evaluation and Review
Technique (PERT)—may not be as fit for purpose as they seem. Arguably, because of their relative simplicity,
these techniques are still almost the only ones taught nowadays in most introductory courses to scheduling in
many engineering and management degrees. However, by utterly ignoring or inappropriately dealing with activity
duration variability, these techniques provide optimistic completion dates, while suffering from other
shortcomings. Through a series of simple case studies that can be developed with a few participants and
common dice, a systematic critique of the classical scheduling techniques is offered. Discussion of the case
studies results illustrate why limiting the contents of scheduling education and teaching can be detrimental, as the
aforementioned classical scheduling techniques cannot not provide project managers with sufficient resources to
effectively plan and control real projects
Review on bio-based plastic for future applications
This paper reviews the future applications of bio-based plastics. Most plastics are
made through petrochemical processes. In other words, they start out as the chemical
byproducts of oil refining, which are turned into a variety of plastics through chemical processes
that form long molecular chains known as polymers. These polymers give plastics their
structure. Bioplastics are biodegradable materials that come from renewable sources and can
be used to reduce the problem of plastic waste that is suffocating the planet and contaminating
the environment. The advantages of using bioplastics are bioplastics won’t leach chemicals into
food, non- toxic and offer a zero waste end life options. Bioplastics can be recycled with
conventional plastics to produce a great material for food packaging. It also has a socio�economic benefit that often have a positive impact on the consumers who are increasingly
becoming aware of environmental issues. As conclusion, it is proven that bioplastics give
promising future to cleaner and safer world
On the duration and cost variability of construction activities: an empirical study
The unique nature of construction projects can mean that construction activities often suffer from duration and cost variability. As this variability is unplanned it can present a problem when attempting to complete a project on time and on budget. Various factors causing this variability have been identified in the literature, but they predominantly refer to the nature and/or context of the whole project, rather than their specific activities. In this paper, the order of magnitude of and correlation between activity duration and cost variability is analyzed in 101 construction projects with over 5000 activities. To do this, the first four moments (mean, standard deviation, skewness and kurtosis) of actual versus planned duration and cost (log) ratios are analyzed by project, phase of execution and activity type. Results suggest that, contrary to common wisdom, construction activities do not end late on average. Instead, the large variability in the activity duration is the major factor causing significant project delays and cost overruns. The values of average activity duration and cost variability gathered in this study will also serve as a reference for construction managers to improve future construction planning and project simulation studies with more realistic data
Least squares approximation to the distribution of project completion times with Gaussian uncertainty
This paper is motivated by the following question: How to construct good approximation for the distribution of the solution value to linear optimization problem when the random objective coefficients follow a multivariate normal distribution? Using Stein’s Identity, we show that the least squares normal approximation of the random optimal value can be computed by estimating the persistency values of the corresponding optimization problem. We further extend our method to construct a least squares quadratic estimator to improve the accuracy of the approximation; in particular, to capture the skewness of the objective. Computational studies show that the new approach provides more accurate estimates of the distributions of project completion times compared to existing methods. </jats:p
Recommended from our members
M-PERT: manual project-duration estimation technique for teaching scheduling basics
The Program Evaluation and Review Technique (PERT) has become a classic Project Management tool for estimating project duration when the activities have uncertain durations. However, despite its simplicity and widespread adoption, the original PERT, in neglecting the merge event bias, significantly underestimated the duration average and overestimated the duration variance of real-life projects. To avoid these and other shortcomings, many authors have worked over the last 60 years at producing interesting alternative PERT extensions. This paper proposes joining the most relevant of those to create a new reformulated PERT, named M-PERT.
M-PERT is quite accurate when estimating real project duration, while also allowing for a number of interesting network modelling features the original PERT lacked: probabilistic alternative paths, activity self-loops, minima of activity sets and correlation between activities. However, unlike similar scheduling methods, M-PERT allows manual calculation through a recursive merging procedure that downsizes the network until the last standing activity represents the whole (or remaining) project duration. Hence, M-PERT constitutes an attractive tool for teaching scheduling basics to engineering students in a more intuitive way, with or without the assistance of computer-based simulations or software. One full case study will also be proposed and future research paths suggested
Persistency and Stein's Identity: Applications in Stochastic Discrete Optimization Problems
Ph.DDOCTOR OF PHILOSOPH
On path correlation and PERT bias
Most studies of project time estimation assume that (a) activity times are mutually independent random variables; many also assume that (b) path completion times are mutually independent. In this paper, we subject the impact of both these assumptions to close scrutiny. Using tools from multivariate analysis, we make a theoretical study of the direction of the error in the classical PERT method of estimating mean project completion time when correlation is ignored. We also investigate the effect of activity dependence on the normality of path length via simulation.