85 research outputs found

    Mechanical dynamic load of the LHC arc cryo-magnets during the installation

    Get PDF
    About 1700 LHC main superconducting dipoles and quadrupoles will have to be transported and handled between the assembly, the magnet measurements and the storage that precedes the final installation in the LHC tunnel. To ensure the required mechanic and geometric integrity of the cryo-magnets, transport specifications and allowed acceleration loads were defined after detailed dynamic analysis. A large number of cryo-magnets are now arriving at CERN on a regular basis. The logistics for the handling and transport are monitored with tri-axial acceleration monitoring devices that are installed on each cryo-magnet. Measurements are made to commission new equipment like overhead cranes, tunnel transport and handling devices to guarantee that the defined acceleration limits are respected. The results from the acceleration monitoring that are stored in the same quality assurance system as the cryo-magnets allowed to give a first idea of the level of the mechanical dynamic load on each magnet throughout the logistics chain and were used to detect details such as out-of-specification accelerations that needed improvement

    TRANSPORT AND INSTALLATION OF CRYO-MAGNETS IN CERN'S LARGE HADRON COLLIDER TUNNEL

    Get PDF
    The arcs of the Large Hadron Collider (LHC) will contain around 1700 main superconducting dipoles and quadrupoles. The long and heavy magnets are supported on fragile composite support posts inside a cryostat to reduce the heat in-leak to the magnets' super fluid helium bath. The presence of fragile components and the need to avoid geometry changes make the cryo-magnets very difficult to handle and transport. The transport and installation of the LHC cryo-magnets in the LEP tunnels originally designed for smaller, lighter LEP magnets has required development of completely new handling solutions. The paper explains the constraints imposed by the cryo-magnet characteristics, the existing tunnel infrastructure and schedule considerations. The development and realisation of transport and handling solutions are described, starting from conceptual design, through manufacture and testing to the installation of the first cryo-magnet. Integration studies to verify and reserve space needed for manoeuvre and the preparation of the infrastructure for transport and installation operations are also presented. The paper includes conclusions and some of the lessons learned

    The Tuning System for the HIE-ISOLDE High-Beta Quarter Wave Resonator

    Full text link
    A new linac using superconducting quarter-wave resonators (QWR) is under construction at CERN in the framework of the HIE-ISOLDE project. The QWRs are made of niobium sputtered on a bulk copper substrate. The working frequency at 4.5 K is 101.28 MHz and they will provide 6 MV/m accelerating gradient on the beam axis with a total maximum power dissipation of 10 W on cavity walls. A tuning system is required in order to both minimize the forward power variation in beam operation and to compensate the unavoidable uncertainties in the frequency shift during the cool-down process. The tuning system has to fulfil a complex combination of RF, structural and thermal requirements. The paper presents the functional specifications and details the tuning system RF and mechanical design and simulations. The results of the tests performed on a prototype system are discussed and the industrialization strategy is presented in view of final production.Comment: 5 pages, The 16th International Conference on RF Superconductivity (SRF2013), Paris, France, Sep 23-27, 201

    Thermal Design and Performance of the Electrical Distribution Feed Box of the LHC prototype cell

    Get PDF
    The Electrical Distribution Feed Box (DFBS) is a 4.5 K saturated liquid helium cryostat constructed for the Large Hadron Collider (LHC) Prototype Cell (String 2). The thermal design of the DFBS is presented, with emphasis on the modelling of the cooling of the current lead chimneys via the helium bath boil-off gas and on the design of the lambda plate. The expected performance is compared to measurements done during the first operation phase of the LHC prototype cell

    Design and Vertical Tests of SPS-series Double-Quarter Wave (DQW) Cavity Prototypes for the HL-LHC Crab Cavity System

    Full text link
    Crab crossing is essential for high-luminosity colliders. The High Luminosity Large Hadron Collider (HL-LHC) will equip one of its Interaction Points (IP1) with Double-Quarter Wave (DQW) crab cavities. A DQW cavity is a new generation of deflecting RF cavities that stands out for its compactness and broad frequency separation between fundamental and first high-order modes. The deflecting kick is provided by its fundamental mode. Each HL-LHC DQW cavity shall provide a nominal deflecting voltage of 3.4 MV, although up to 5.0 MV may be required. A Proof-of-Principle (PoP) DQW cavity was limited by quench at 4.6 MV. This paper describes a new, highly optimized cavity, designated DQW SPS-series, which satisfies dimensional, cryogenic, manufacturing and impedance requirements for beam tests at SPS and operation in LHC. Two prototypes of this DQW SPS-series were fabricated by US industry and cold tested after following conventional SRF surface treatment. Both units outperformed the PoP cavity, reaching a deflecting voltage of 5.3-5.9 MV. This voltage - the highest reached by a DQW cavity - is well beyond the nominal voltage of 3.4 MV and may even operate at the ultimate voltage of 5.0MVwith sufficient margin. This paper covers fabrication, surface preparation and cryogenic RF test results and implications

    Study of the Stabilization to the Nanometer Level of Mechanical Vibrations of the CLIC Main Beam

    Get PDF
    Original publication available at http://www.jacow.org/International audienceTo reach the design luminosity of CLIC, the movements of the quadrupoles should be limited to the nanometre level in order to limit the beam size and emittance growth. Below 1 Hz, the movements of the main beam quadrupoles will be corrected by a beambased feedback. But above 1 Hz, the quadrupoles should be mechanically stabilized. A collaboration effort is ongoing between several institutes to study the feasibility of the "nanostabilization" of the CLIC quadrupoles. The study described in this paper covers the characterization of independent measuring techniques including optical methods to detect nanometre sized displacements and analyze the vibrations. Actuators and feedback algorithms for sub-nanometre movements of magnets with a mass of more than 400 kg are being developed and tested. Input is given to the design of the quadrupole magnets, the supports and alignment system in order to limit the amplification of the vibration sources at resonant frequencies. A full scale mock-up integrating all these features is presently under design. Finally, a series of experiments in accelerator environments should demonstrate the feasibility of the nanometre stabilization

    Overview of the Large Hadron Collider cryo-magnets logistics

    Get PDF
    More than 1700 superconducting cryo-magnets have to be installed in the Large Hadron Collider tunnel. The long, heavy and fragile LHC cryo-magnets are difficult to handle and transport in particular in the LEP tunnel environment originally designed for smaller, lighter LEP magnets. An installation rate of more than 20 cryo-magnets per week is needed to cope with the foreseen LHC installation end date. The paper gives an overview of the transport and installation sequence complexity, from the storage area at the surface to the cryo-magnet final position in the tunnel. The success of this task depends on a series of independent factors that have to be considered at the same time. The equipment needed for the transport and tunnel installation of the LHC cryo-magnets is briefly described. The manpower and equipment organisation as well as the challenges of logistics are then detailed. The paper includes conclusions and some of the lessons learned during the first phase of the LHC cryo-magnets installation

    First Results and Status of the LHC Test String 2

    Get PDF
    After the commissioning of String 2 Phase1 and the powering of the main circuits in autumn 2001, a short yet vigorous experimental program was carried-out to validate the final design choices for the technical systems of LHC. This program included the investigation of thermo-hydraulics of quenches quench propagation, power converter controls and tracking between power converters, as well as the measurement of currents induced in the beam screen after a quench and crossing the interconnects. Parameters significant for the LHC, such as heat loads, were also measured. During the winter shutdown the String was completed to a full cell with the addition of three pre-series dipoles (Phase 2). After a short description of the layout of Phase 1 and Phase 2, the results of the experiments are presented and the future experimental program is outlined
    • …
    corecore