696 research outputs found

    Optimization-Based Architecture for Managing Complex Integrated Product Development Projects

    Get PDF
    By the mid-1990\u27s, the importance of early introduction of new products to both market share and profitability became fully understood. Thus, reducing product time-to-market became an essential requirement for continuous competition. Integrated Product Development (IPD) is a holistic approach that helps to overcome problems that arise in a complex product development project. IPD emphasis is to provide a framework for an effective planning and managing of engineering projects. Coupled with the fact that about 70% of the life cycle cost of a product is committed at early design phases, the motivation for developing and implementing more effective methodologies for managing the design process of IPD projects became very strong. The main objective of this dissertation is to develop an optimization-based architecture that helps guiding the project manager efforts for managing the design process of complex integrated product development projects. The proposed architecture consists of three major phases: system decomposition, process re-engineering, and project scheduling and time-cost trade-off analysis. The presented research contributes to five areas of research: (1) Improving system performance through efficient re-engineering of its structure. The Dependency Structure Matrix (DSM) provides an effective tool for system structure understanding. An optimization algorithm called Simulated Annealing (SA) was implemented to find an optimal activity sequence of the DSM representing a design project. (2) A simulation-based optimization framework that integrates simulated annealing with a commercial risk analysis software called Crystal Ball was developed to optimally re-sequence the DSM activities given stochastic activity data. (3) Since SA was originally developed to handle deterministic objective functions, a modified SA algorithm able to handle stochastic objective functions was presented. (4) A methodology for the conversion of the optimally sequenced DSM into an equivalent DSM, and then into a project schedule was proposed. (5) Finally, a new hybrid time-cost trade-off model based on the trade-off of resources for project networks was presented. These areas of research were further implemented through a developed excel add-in called “optDSM”. The tool was developed by the author using Visual Basic for Application (VBA) programming language

    The Project Scheduling Problem with Non-Deterministic Activities Duration: A Literature Review

    Get PDF
    Purpose: The goal of this article is to provide an extensive literature review of the models and solution procedures proposed by many researchers interested on the Project Scheduling Problem with nondeterministic activities duration. Design/methodology/approach: This paper presents an exhaustive literature review, identifying the existing models where the activities duration were taken as uncertain or random parameters. In order to get published articles since 1996, was employed the Scopus database. The articles were selected on the basis of reviews of abstracts, methodologies, and conclusions. The results were classified according to following characteristics: year of publication, mathematical representation of the activities duration, solution techniques applied, and type of problem solved. Findings: Genetic Algorithms (GA) was pointed out as the main solution technique employed by researchers, and the Resource-Constrained Project Scheduling Problem (RCPSP) as the most studied type of problem. On the other hand, the application of new solution techniques, and the possibility of incorporating traditional methods into new PSP variants was presented as research trends. Originality/value: This literature review contents not only a descriptive analysis of the published articles but also a statistical information section in order to examine the state of the research activity carried out in relation to the Project Scheduling Problem with non-deterministic activities duration.Peer Reviewe

    Resource Schedule of Concrete Fish Pond Construction Using Network Analysis

    Get PDF
    In the construction of building, preparation of bid, maintenance and planning of oil refinery and preparation for agricultural activities, there is a need to know the completion days of the project without delay and the earliest time and the latest time for which each activity will take. It was based on this that we decide to analyze the construction of concrete fish pond using Network Analysis through the use of Critical Path Method (CPM) and Program Evaluation Review Technique (PERT). Sixty-four days was arrived at for the completion of the construction using CPM while sixty-eight days with 99% probability was arrived at using PERT method. In deciding which of the method is best suitable for the construction of the fish pond, PERT serve as the best method due to the fact that it considers the Pessimistic Time (longest time possible and can be seen as usual delay) and Optimistic Time (shortest time possible if things go perfectly) as well as the probability [which is 99%] of completing the task within a specific time. The result established some useful facts for researchers in this area as well as managers of industry in carrying out their study from the feasibility stage to the other stages so as to have a good practical target towards the completion of the project as planned. Keyword: Network Analysis, Critical Path Method, Program Evaluation Review Technique, Pessimistic Time, Optimistic Time and Probability DOI: 10.7176/JMCR/57-04 Publication date:June 30th 201

    Railway scheduling reduces the expected project makespan.

    Get PDF
    The Critical Chain Scheduling and Buffer Management (CC/BM) methodology, proposed by Goldratt (1997), introduced the concepts of feeding buffers, project buffers and resource buffers as well as the roadrunner mentality. This last concept, in which activities are started as soon as possible, was introduced in order to speed up projects by taking advantage of predecessors finishing early. Later on, the railway scheduling concept of never starting activities earlier than planned was introduced as a way to increase the stability of the project, typically at the cost of an increase in the expected project makespan. In this paper, we will indicate a realistic situation in which railway scheduling improves both the stability and the expected project makespan over roadrunner scheduling.Railway scheduling; Roadrunner scheduling; Feeding buffer; Priority list; Resource availability;

    Four payment models for the multi-mode resource constrained project scheduling problem with discounted cash flows

    Get PDF
    In this paper, the multi-mode resource constrained project scheduling problem with discounted cash flows is considered. The objective is the maximization of the net present value of all cash flows. Time value of money is taken into consideration, and cash in- and outflows are associated with activities and/or events. The resources can be of renewable, nonrenewable, and doubly constrained resource types. Four payment models are considered: Lump sum payment at the terminal event, payments at prespecified event nodes, payments at prespecified time points and progress payments. For finding solutions to problems proposed, a genetic algorithm (GA) approach is employed, which uses a special crossover operator that can exploit the multi-component nature of the problem. The models are investigated at the hand of an example problem. Sensitivity analyses are performed over the mark up and the discount rate. A set of 93 problems from literature are solved under the four different payment models and resource type combinations with the GA approach employed resulting in satisfactory computation times. The GA approach is compared with a domain specific heuristic for the lump sum payment case with renewable resources and is shown to outperform it

    Resource dedication problem in a multi-project environment

    Get PDF
    There can be different approaches to the management of resources within the context of multi-project scheduling problems. In general, approaches to multiproject scheduling problems consider the resources as a pool shared by all projects. On the other hand, when projects are distributed geographically or sharing resources between projects is not preferred, then this resource sharing policy may not be feasible. In such cases, the resources must be dedicated to individual projects throughout the project durations. This multi-project problem environment is defined here as the resource dedication problem (RDP). RDP is defined as the optimal dedication of resource capacities to different projects within the overall limits of the resources and with the objective of minimizing a predetermined objective function. The projects involved are multi-mode resource constrained project scheduling problems with finish to start zero time lag and non-preemptive activities and limited renewable and nonrenewable resources. Here, the characterization of RDP, its mathematical formulation and two different solution methodologies are presented. The first solution approach is a genetic algorithm employing a new improvement move called combinatorial auction for RDP, which is based on preferences of projects for resources. Two different methods for calculating the projects’ preferences based on linear and Lagrangian relaxation are proposed. The second solution approach is a Lagrangian relaxation based heuristic employing subgradient optimization. Numerical studies demonstrate that the proposed approaches are powerful methods for solving this problem

    An overview of recent research results and future research avenues using simulation studies in project management

    Get PDF
    This paper gives an overview of three simulation studies in dynamic project scheduling integrating baseline scheduling with risk analysis and project control. This integration is known in the literature as dynamic scheduling. An integrated project control method is presented using a project control simulation approach that combines the three topics into a single decision support system. The method makes use of Monte Carlo simulations and connects schedule risk analysis (SRA) with earned value management (EVM). A corrective action mechanism is added to the simulation model to measure the efficiency of two alternative project control methods. At the end of the paper, a summary of recent and state-of-the-art results is given, and directions for future research based on a new research study are presented

    A Computer Modeling Approach Using Critical Resource Diagramming Network Analysis in Project Scheduling

    Get PDF
    The problem of resource constrained project scheduling (RCPSP) continues to be an important topic in project management. Different scheduling processes have been introduced to solve cases of RCPSP. Most of the developed methods are based on a network analysis approach. The two main technique of project network analysis used for planning, scheduling, and control are PERT and CPM. These approaches assume unlimited resource availability in project network analysis. In realistic projects, both the time and resource requirements of activities should be considered in developing network schedules. Another particularity of the methods created, so far, is the focus on activities during the scheduling process. Therefore, from a resource point of view, the current procedures do not allow the project manager to incorporate information concerning each resource unit under supervision in the scheduling process of a project. There is a need for simple tools for resource planning, scheduling, tracking, and control. Critical resource diagramming (CRD) is a relatively new resource management tool. CRD is a simple extension to the CPM technique developed for resource management purposes. Unlike activity networks, CRD uses nodes to represent each resource unit. Also, contrasting with activities, a resource unit may appear more than once in a CRD network, specifying all different tasks to which a particular unit is assigned. Similar to CPM, the same backward and forward computations may be performed to CRD. The CRD method can also be used in solving RCPSP problems. This present study explores that advantage of CRD. The purposes are to develop a methodology, based on CRD, which allows its use in specific case of RCPSP, to implement the developed technique using a computer model, to conduct test to validate the CRD computer model, and then to investigate the advantages and disadvantages of the introduced method. The CRD computer model will be implemented using the Visual Basic 6.0 language

    Project network models with discounted cash flows. A guided tour through recent developments.

    Get PDF
    The vast majority of the project scheduling methodologies presented in the literature have been developed with the objective of minimizing the project duration subject to precedence and other constraints. In doing so, the financial aspects of project management are largely ignored. Recent efforts have taken into account discounted cash flow and have focused on the maximalization of the net present value (npv) of the project as the more appropriate objective. In this paper we offer a guided tour through the important recent developments in the expanding field of research on deterministic and stochastic project network models with discounted cash flows. Subsequent to a close examination of the rationale behind the npv objective, we offer a taxonomy of the problems studied in the literature and critically review the major contributions. Proper attention is given to npv maximization models for the unconstrained scheduling problem with known cash flows, optimal and suboptimal scheduling procedures with various types of resource constraints, and the problem of determining both the timing and amount of payments.Scheduling; Models; Model; Discounted cash flow; Cash flow; Project scheduling; Project management; Management; Net present value; Value; Problems; Maximization; Optimal;
    • …
    corecore