13,003 research outputs found

    The Project Scheduling Problem with Non-Deterministic Activities Duration: A Literature Review

    Get PDF
    Purpose: The goal of this article is to provide an extensive literature review of the models and solution procedures proposed by many researchers interested on the Project Scheduling Problem with nondeterministic activities duration. Design/methodology/approach: This paper presents an exhaustive literature review, identifying the existing models where the activities duration were taken as uncertain or random parameters. In order to get published articles since 1996, was employed the Scopus database. The articles were selected on the basis of reviews of abstracts, methodologies, and conclusions. The results were classified according to following characteristics: year of publication, mathematical representation of the activities duration, solution techniques applied, and type of problem solved. Findings: Genetic Algorithms (GA) was pointed out as the main solution technique employed by researchers, and the Resource-Constrained Project Scheduling Problem (RCPSP) as the most studied type of problem. On the other hand, the application of new solution techniques, and the possibility of incorporating traditional methods into new PSP variants was presented as research trends. Originality/value: This literature review contents not only a descriptive analysis of the published articles but also a statistical information section in order to examine the state of the research activity carried out in relation to the Project Scheduling Problem with non-deterministic activities duration.Peer Reviewe

    Railway scheduling reduces the expected project makespan.

    Get PDF
    The Critical Chain Scheduling and Buffer Management (CC/BM) methodology, proposed by Goldratt (1997), introduced the concepts of feeding buffers, project buffers and resource buffers as well as the roadrunner mentality. This last concept, in which activities are started as soon as possible, was introduced in order to speed up projects by taking advantage of predecessors finishing early. Later on, the railway scheduling concept of never starting activities earlier than planned was introduced as a way to increase the stability of the project, typically at the cost of an increase in the expected project makespan. In this paper, we will indicate a realistic situation in which railway scheduling improves both the stability and the expected project makespan over roadrunner scheduling.Railway scheduling; Roadrunner scheduling; Feeding buffer; Priority list; Resource availability;

    Project scheduling under undertainty – survey and research potentials.

    Get PDF
    The vast majority of the research efforts in project scheduling assume complete information about the scheduling problem to be solved and a static deterministic environment within which the pre-computed baseline schedule will be executed. However, in the real world, project activities are subject to considerable uncertainty, that is gradually resolved during project execution. In this survey we review the fundamental approaches for scheduling under uncertainty: reactive scheduling, stochastic project scheduling, stochastic GERT network scheduling, fuzzy project scheduling, robust (proactive) scheduling and sensitivity analysis. We discuss the potentials of these approaches for scheduling projects under uncertainty.Management; Project management; Robustness; Scheduling; Stability;

    A classification of predictive-reactive project scheduling procedures.

    Get PDF
    The vast majority of the project scheduling research efforts over the past several years have concentrated on the development of workable predictive baseline schedules, assuming complete information and a static and deterministic environment. During execution, however, a project may be subject to numerous schedule disruptions. Proactive-reactive project scheduling procedures try to cope with these disruptions through the combination of a proactive scheduling procedure for generating predictive baseline schedules that are hopefully robust in that they incorporate safety time to absorb anticipated disruptions with a reactive procedure that is invoked when a schedule breakage occurs during project execution.proactive-reactive project scheduling; time uncertainty; stability; timely project completion; preselective strategies; resource constraints; trade-off; complexity; stability; management; makespan; networks; subject; job;

    Employee substitutability as a tool to improve the robustness in personnel scheduling

    Get PDF

    Design project planning, monitoring and re-planning through process simulation

    Get PDF
    Effective management of design schedules is a major concern in industry, since timely project delivery can have a significant influence on a company’s profitability. Based on insights gained through a case study of planning practice in aero-engine component design, this paper examines how task network simulation models can be deployed in a new way to support design process planning. Our method shows how simulation can be used to reconcile a description of design activities and information flows with project targets such as milestone delivery dates. It also shows how monitoring and re-planning can be supported using the non-ideal metrics which the case study revealed are used to monitor processes in practice. The approach is presented as a theoretical contribution which requires further work to implement and evaluate in practice

    On the construction of stable project baseline schedules.

    Get PDF
    The vast majority of project scheduling efforts assume complete information about the scheduling problem to be solved and a static deterministic environment within which the pre-computed baseline schedule will be executed. In reality, however, project activities are subject to considerable uncertainty, which generally leads to numerous schedule disruptions. It is of interest to develop pre-schedules that can absorb disruptions in activity durations without affecting the planning of other activities, such that co-ordination of resources and material procurement for each of the activities can be performed as smoothly as possible. The objective of this paper is to develop and evaluate various approaches for constructing a stable pre-schedule, which is unlikely to undergo major changes when it needs to be repaired as a reaction to minor activity duration disruptions.

    A branch-and-bound algorithm for stable scheduling in single-machine production systems.

    Get PDF
    Robust scheduling aims at the construction of a schedule that is protected against uncertain events. A stable schedule is a robust schedule that will change little when variations in the input parameters arise. This paper proposes a branch-and-bound algorithm for optimally solving a single-machine scheduling problem with stability objective, when a single job is anticipated to be disrupted.Branch-and-bound; Construction; Event; Job; Robust scheduling; Robustness; Scheduling; Single-machine scheduling; Stability; Systems; Uncertainty;

    ROBUST RESOURCE INVESTMENT PROBLEM WITH TIME-DEPENDENT RESOURCE COST AND TARDINESS PENALTY

    Get PDF
    The Resource Investment Problem (RIP) is a variant of the well-known Resource Constraint Project Scheduling Problem (RCPSP) that requires finding the optimal resource allocation, given a preset completion date, with the objective of minimizing the total cost. The practical relevance of RIP is very obvious; since the decision maker (the project manager for example) wants to know what resources are required to achieve the targeted project completion date. RIP helps to decide the amount of investment in resources that yield the optimal solution, in addition to the optimal tradeoff between completion time and resource investment. In practice, most of the projects are associated with due dates beyond which a tardiness penalty may be applied. To avoid the tardiness penalty, project managers sometimes decide to add more resources, thereby increasing resource investment cost, to the project to finish earlier. In this thesis the (RIP) has been extended to consider time-depended resource cost instead of time-independent resource cost in the classical RIP. The problem was named Resource Investment Problem with Time-Dependent Resource Cost and Tardiness Penalty, abbreviated as (RIP-TDRC). A mathematical model was introduced to simultaneously find the optimal resource assignment and activity staring times. The objective is to minimize the sum of the resources and tardiness cost. Two versions of this problem are addressed in this thesis: the deterministic version of RIP-TDRC and the stochastic version. For the latter, it is assumed that the activity durations are subject to many uncertainties such as (bad weather conditions, material shortage, employee’s absences …etc.). To solve this problem, a simulation-optimization based algorithm is proposed. This algorithm solves the deterministic problem version iteratively through all possible project completion times and simulates the project considering the uncertainties to find the optimal solution. The performance of the proposed algorithm and the effect of some problem parameters on the solution are assessed through computational experiments. The experiments revealed the usefulness of the algorithm in finding relatively robust solution for small problem sizes
    corecore