6 research outputs found
Recommended from our members
Duration and cost variability of construction activities: an empirical study
The unique nature of construction projects can mean that construction activities often suffer from duration and cost variability. Because this variability is unplanned, it can present a problem when attempting to complete a project on time and on budget. Various factors causing this variability have been identified in the literature, but they predominantly refer to the nature and/or context of the whole project rather than specific activities. In this paper, the order of magnitude of and correlation between activity duration and cost variability is analyzed in 101 construction projects with over 5,000 activities. To do this, the first four moments (mean, standard deviation, skewness, and kurtosis) of actual versus planned duration and cost (log) ratios are analyzed by project, phase of execution, and activity type. Results suggest that, contrary to common wisdom, construction activities do not end late on average. Instead, the large variability in the activity duration is the major factor causing significant project delays and cost overruns. The values of average activity duration and cost variability gathered in this study will also serve as a reference for construction managers to improve future construction planning and project simulation studies with more realistic data
Setting tolerance limits for statistical project control using earned value management
Project control has been a research topic since decades that attracts both academics and practitioners. Project control systems indicate the direction of change in preliminary planning variables compared with actual performance. In case their current project performance deviates from the planned performance, a warning is indicated by the system in order to take corrective actions.
Earned value management/earned schedule (EVM/ES) systems have played a central role in project control, and provide straightforward key performance metrics that measure the deviations between planned and actual performance in terms of time and cost. In this paper, a new statistical project control procedure sets tolerance limits to improve the discriminative power between progress situations that are either statistically likely or less likely to occur under the project baseline schedule. In this research, the tolerance limits are derived from subjective estimates for the activity durations of the project. Using the existing and commonly known EVM/ES metrics, the resulting project control charts will have an improved ability to trigger actions when variation in a projectืณs progress exceeds certain predefined thresholds
A computational experiment has been set up to test the ability of these statistical project control charts to discriminate between variations that are either acceptable or unacceptable in the duration of the individual activities. The computational experiments compare the use of statistical tolerance limits with traditional earned value management thresholds and validate their power to report warning signals when projects tend to deviate significantly from the baseline schedule
On the duration and cost variability of construction activities: an empirical study
The unique nature of construction projects can mean that construction activities often suffer from duration and cost variability. As this variability is unplanned it can present a problem when attempting to complete a project on time and on budget. Various factors causing this variability have been identified in the literature, but they predominantly refer to the nature and/or context of the whole project, rather than their specific activities. In this paper, the order of magnitude of and correlation between activity duration and cost variability is analyzed in 101 construction projects with over 5000 activities. To do this, the first four moments (mean, standard deviation, skewness and kurtosis) of actual versus planned duration and cost (log) ratios are analyzed by project, phase of execution and activity type. Results suggest that, contrary to common wisdom, construction activities do not end late on average. Instead, the large variability in the activity duration is the major factor causing significant project delays and cost overruns. The values of average activity duration and cost variability gathered in this study will also serve as a reference for construction managers to improve future construction planning and project simulation studies with more realistic data
Schedule network node time distributions and arrow criticalities
This research develops exact methods to calculate project duration distributions and to calculate Van Slyke\u27s (1963) criticality for arrows, the probability that an arrow is on a critical path, assuming nonnegative integer duration distributions. These calculations for project duration distributions correct estimates made by the Program Evaluation and Review Technique (PERT), and the Van Slyke criticality calculations extend the arrow criticality analysis by the Critical Path Method (CPM) into the probabilistic realm;Exact methods for calculating project duration distributions and Van Slyke\u27s criticality are demonstrated on series networks, parallel networks, parallel-series networks, and the Wheatstone network. The Van Slyke criticality equation for parallel networks is in a form that appears to improve upon one proposed by Dodin & Elmaghraby (1985). The present form is generalized to, in principle, include all networks;The exact methods are enhanced by developing a procedure to limit the number of calculations needed to analyze large networks. The procedure identifies paths through a large network, calculates the minimum and maximum path durations, and ranks the paths by duration. A smaller skeletal network is constructed from the arrows of the longest paths and is analyzed by exact methods. The procedure emphasizes accuracy for the longer project durations, of greatest concern to project managers and schedulers, while limiting the number of necessary calculations;The procedure for large networks is illustrated on the 40-arrow Kleindorfer (1971) network. Of the 51 Kleindorfer paths, the procedure selected 6 paths to construct a skeletal network. Analysis of the skeletal network yields a project duration distribution that is correct in its range and in the duration probabilities for the upper 5% of the distribution. Analysis results are compared with SLAM II and FORTRAN simulations. No arrow criticality appears to be seriously miscalculated. The project duration distribution is calculated to be bimodal, in keeping with the simulation;Conditions under which the just mentioned bimodality can occur are determined for parallel, normally-distributed paths. The large-network procedure warns when these oddly shaped distributions are possible
Recommended from our members
M-PERT: manual project-duration estimation technique for teaching scheduling basics
The Program Evaluation and Review Technique (PERT) has become a classic Project Management tool for estimating project duration when the activities have uncertain durations. However, despite its simplicity and widespread adoption, the original PERT, in neglecting the merge event bias, significantly underestimated the duration average and overestimated the duration variance of real-life projects. To avoid these and other shortcomings, many authors have worked over the last 60 years at producing interesting alternative PERT extensions. This paper proposes joining the most relevant of those to create a new reformulated PERT, named M-PERT.
M-PERT is quite accurate when estimating real project duration, while also allowing for a number of interesting network modelling features the original PERT lacked: probabilistic alternative paths, activity self-loops, minima of activity sets and correlation between activities. However, unlike similar scheduling methods, M-PERT allows manual calculation through a recursive merging procedure that downsizes the network until the last standing activity represents the whole (or remaining) project duration. Hence, M-PERT constitutes an attractive tool for teaching scheduling basics to engineering students in a more intuitive way, with or without the assistance of computer-based simulations or software. One full case study will also be proposed and future research paths suggested
Analysis of Integrated Reliability for Heterogeneous Events
ํ์๋
ผ๋ฌธ (๋ฐ์ฌ)-- ์์ธ๋ํ๊ต ๋ํ์ : ์ํ์กฐ๊ฒฝยท์ง์ญ์์คํ
๊ณตํ๋ถ(์ง์ญ์์คํ
๊ณตํ์ ๊ณต), 2015. 8. ์ด์ ์ฌ.๋ณธ ์ฐ๊ตฌ๋ ๋ถํ์ค์ฑ์ ๊ฐ๋ ๊ฐ๋ณ ํ๋ฅ ์ฌ์๋ค์ด ๊ฒฐํฉ๋ ์์ฐํ์์ ๊ฐ๋ณ ์์๊ฐ์ ์ธ์ ์ฑ๊ณผ ๊ด๊ณ์์ด ์ฐ๊ฒฐ์ฑ์ ์ง๋ฐฐ๋ฅผ ๋ฐ๋ ์์๊ตฌ์กฐ์, ์ธ์ ์์๋ค๊ณผ์ ๋ฌผ๋ฆฌ์ ๊ฑฐ๋ฆฌ์ ์ง๋ฐฐ๋ฅผ ๋ฐ๋ ๊ธฐํ๊ตฌ์กฐ๋ก ๊ตฌ๋ถํ๊ณ , ์ด๋ค์ ๋ํด ํ๋ฅ ์ฌ๊ท๊ฒฉํ๋ฅผ ์ด์ฉํ ์์คํ
์ ๋ขฐ์ฑํด์ ๋ฐฉ๋ฒ์ ์ ์ํ์๋ค.
์ผ๋ฐ์ ์ผ๋ก ๋๋ถ๋ถ์ ๊ณตํ๋ฌธ์ ๋ ๊ฒฐ์ ๋ก ์ ๋ฐฉ๋ฒ๋ก ์ ํตํด ์์ฐํ์์ ์ค๋ช
ํ๋ ์ง๋ฐฐ๋ฐฉ์ ์์ ์ ์ํ๊ณ , ์ด๋ฅผ ๊ตฌ์ฑํ๋ ๊ณ์์ ์ด๊ธฐ์กฐ๊ฑด, ๊ฒฝ๊ณ์กฐ๊ฑด์ ์ง๋ฐฐ๋ฐฉ์ ์์ ๋์
ํ์ฌ ํด์ํ๋ค. ๊ทธ๋ฌ๋ ์ง๋ฐฐ๋ฐฉ์ ์์ ํ์ํ ์ฌ๋ฌ ์กฐ๊ฑด๊ณผ ๊ณ์๋ ์ธก์ ํน์ ์ถ์ ์ ์์กดํด์ผ ํ๋ฏ๋ก ๋ถํ์ค์ฑ์ ๋ดํฌํ๊ฒ ๋๋ค. ๋ถํ์ค์ฑ์ ๊ณ ๋ คํ๊ธฐ ์ํ์ฌ ํ๋ฅ ๋ก ์ ํด์์ ๊ธฐ๋ฐํ ์ ๋ขฐ์ฑ ํด์๊ธฐ๋ฒ๋ค์ด ์ฌ๋ฌ ๋ถ์ผ์ ๋์
๋์์ผ๋, ๋จ์ ์ฌ์์ด ์๋ ์ฌ๋ฌ ์ฌ์์ด ๊ฒฐํฉ๋์ด ์๋ ๋ฌธ์ ์์๋ ์ด๋ฅผ ์ ์ฉํ๊ธฐ ์ด๋ ค์ ๋ค. ๋ชฌํ
์นด๋ฅผ๋ก ์๋ฎฌ๋ ์ด์
๋ฑ์ ๊ธฐ๋ฒ์ผ๋ก ๊ณ์ฐํ๋ ๋ฐฉ๋ฒ๋ ์ ์๋์์ผ๋, ๋ณตํฉ์ฌ์์ ๋ณต์ก์ฑ์ด ์ฆ๊ฐํ ์๋ก ๊ณ์ฐ๋๋ ๊ธฐํ๊ธ์์ ์ผ๋ก ์ฆ๊ฐํ๋ ํ๊ณ๊ฐ ์์๋ค. ๋ฐ๋ผ์ ๋ณธ ์ฐ๊ตฌ์์๋ ๋ณตํฉ์ฌ์์ ์์๊ตฌ์กฐ ๋ฌธ์ ์ ๊ธฐํ๊ตฌ์กฐ ๋ฌธ์ ๋ก ๋จ์ํ ํ๊ณ ํ๋ฅ ์ฌ๊ท๊ฒฉํ๋ฅผ ํตํด ์ ๋ขฐ์ฑํด์ ํ๋ ๋ฐฉ๋ฒ์ ์ ์ํ์๋ค.
์์๊ตฌ์กฐ์ ๋ณตํฉํ๋ฅ ์ฌ์์ ๊ณ์ธต๊ตฌ์กฐ๋ก ๋ณํํ ํ, ๊ฐ์ ์์ ์ฌ์์ ๊ณต์ ํ๋ ํ์ ํ๋ฅ ์ฌ์๋ค์ ํ๋ฅ ์ฌ๊ท๊ฒฉํ๋ฅผ ์ด์ฉํด ๊ฒฐํฉํจ์ผ๋ก์จ ์์ ์ฌ์์ ํ๋ฅ ์ฌ์์ ์ฐ์ ํ ์ ์๊ณ , ์ด๋ฅผ ๋ฐ๋ณตํ์ฌ ์์คํ
์ ์ฒด์ ์ ๋ขฐ์ฑ์ ํด์ํ ์ ์๋ค. ๋ณธ ์ฐ๊ตฌ์์๋ ์ด์ ๋ํ ์ ์ฉ์ฑ์ ๊ณ ์ฐฐํ๊ธฐ ์ํ์ฌ ๋์
์ฉ์ ์์ง์ ์ฌํด์ ๋ํ ์ํ๋๋ฅผ ํ์, ์ง์ง์ผ๋ก ์ธํ ์ ์ฒด๋ถ๊ดด, ์์๊ธ๊ฐํ๋ก ์ธํ ์ ์ฒด๋ถ๊ดด์ ์กฐ๊ฑด์ ๋ํ์ฌ ๋ถ์ํ์๋ค.
๊ธฐํ๊ตฌ์กฐ์ ๋ณตํฉํ๋ฅ ์ฌ์์ ๋ฏธ๋ถ๋ฐฉ์ ์์ผ๋ก ์ ์๋๋ ์ฐ์์ฒด ๋ฌธ์ ๋ฅผ ์ ๋ขฐ์ฑ ํด์ํ๋ ๊ณผ์ ์ด๋ค. ๋ฏธ๋ถ๋ฐฉ์ ์์ ์์นํด์ํ๊ธฐ ์ํด ์ ํ์ฐจ๋ถ๋ฒ, ์ ํ์์๋ฒ ๋ฑ์ ๋ฐฉ๋ฒ์ผ๋ก ์ด์ฐํํ๋ฉด, ์ฐ์์ฒด ๋ฌธ์ ๋ฅผ ์ด์ฐํ๋ ์ธ์ ์์๊ฐ์ ์ ๋ณด๊ตํ๊ณผ์ ์ผ๋ก ๋จ์ํ ํ ์ ์๋ค. ์ด๋ค ๊ฐ๋ณ ์์์ ๊ฐ์ด ํ์ ๊ฐ์ด ์๋ ๋ถํ์ค์ฑ์ ๋ดํฌํ ๊ฐ์ธ ๊ฒฝ์ฐ, ์ด ๊ฐ๋ณ ์์์ ํ๋ฅ ์ฌ์์ ํ๋ฅ ์ฌ๊ท๊ฒฉํ๋ฅผ ํตํด ๊ณ์ฐํ ์ ์๋ค. ์ด ๋ฐฉ๋ฒ๋ก ์ ๋ํ ๊ฒ์ฆ์ ์ํ์ฌ ๊ฒฝ๊ณ์กฐ๊ฑด๊ณผ ์ด๊ธฐ์กฐ๊ฑด์ด ํ๋ฅ ๋ถํฌ๋ก ์กด์ฌํ๋ ์ดํ์ฐ๋ฌธ์ ์ ์ ์ฉํ์์ผ๋ฉฐ, ํ์ฉ์๋ก ๋ฐฐ์๊ฐ๋ฌธ ์ฝํฌ๋ฆฌํธ ๊ตฌ์กฐ๋ฌผ์ ์ผํ์ด์จ ํ์ฐ๋ฌธ์ ์ ์ ์ฉํ๊ณ ์๊ฐ์ ๋ฐ๋ฅธ ์ฝํฌ๋ฆฌํธ ๊น์ด๋ณ ์ ๋ขฐ๋๋ฅผ ์ฐ์ ํ์๋ค.
๋ณธ ๋
ผ๋ฌธ์์ ์ ์ํ๋ ๋ฐฉ๋ฒ์ ์์คํ
์ ์ฒด์ ์ ๋ขฐ๋ ํ๊ฐ์ ์์คํ
์ ๊ตฌ์ฑํ๋ ๊ฐ๋ณ ์์๋ค์ ์ ๋ขฐ๋ ํ๊ฐ๋ฅผ ๋์์ ์ํํ ์ ์๋ค๋ ์ด์ ์ด ์๋ค. ์ด๋ฅผ ์ด์ฉํด ๋ค์ํ ์ง์ญ์ ์ฌ๋์ ๋ํ ์ํ๋๋ฅผ ํ๋ฅ ์ ์ผ๋ก ํ๊ฐํ๊ฑฐ๋, ๊ตฌ์กฐ๋ฌผ์ ์ทจ์ฝ์ ์ ์ฐพ์๋ด๋ ๋ฑ์ผ๋ก ํ์ฉ๋ ์ ์์ ๊ฒ์ด๋ค.๊ฐ์คํ๋ฅ ์ฌ๊ท๊ฒฉํ๋ฅผ ์ด์ฉํ ๋ณตํฉ์ฌ์์ ์ ๋ขฐ์ฑํด์ 1
๊ตญ ๋ฌธ ์ด ๋ก 1
1 ์ ๋ก 9
1.1 ์ฐ๊ตฌ๋ฐฐ๊ฒฝ 9
1.2 ์ฐ๊ตฌ๋ด์ฉ ๋ฐ ๋ฒ์ 12
1.3 ๋
ผ๋ฌธ๊ตฌ์ฑ 14
2 ์ฐ๊ตฌ์ฌ 16
2.1 ํ๋ฅ ๋ก 16
2.2 ์ํ๋ 18
2.3 ํ๋ฅ ์ฌ๊ท๊ฒฉํ 19
2.4 ๋ณตํฉ์ฌ์๊ณผ ๋คํธ์ํฌ 21
2.4.1 ์์๊ตฌ์กฐ์ ๋ณตํฉํ๋ฅ ์ฌ์ 22
2.4.2 ๊ธฐํ๊ตฌ์กฐ์ ๋ณตํฉํ๋ฅ ์ฌ์ 23
3 ๋ณตํฉ์ฌ์๊ณผ ํ๋ฅ ์ฌ๊ท๊ฒฉํ 25
3.1 ํ๋ฅ ๋ณตํฉ์ฌ์๊ณผ ๊ฐ์คํ๋ฅ ์ฌ๊ท๊ฒฉํ 25
3.2 ๊ฐ์คํ๋ฅ ์ฌ๊ท๊ฒฉํ์ ์ ์ฉ 28
3.2.1 ์์๊ตฌ์กฐ๋ฅผ ๊ฐ๋ ๋ณตํฉ์ฌ์์ ์ ์ฉ 28
3.2.2 ๊ธฐํ๊ตฌ์กฐ๋ฅผ ๊ฐ๋ ๋ณตํฉ์ฌ์์ ์ ์ฉ 29
4 ์์๊ตฌ์กฐ๋ฅผ ๊ฐ๋ ๋ณตํฉํ๋ฅ ์ฌ์์ ํด์ 30
4.1 ํ๋ฅ ๋ณตํฉ์ฌ์๊ณผ ์ํ๋ 30
4.1.1 ์ํ๋์ ๊ณ์ธต๊ตฌ์กฐํ 30
4.1.2 ๊ฐ์คํ๋ฅ ์ฌ๊ท๊ฒฉํ 31
4.1.3 ๋น๋ชจ์์ ์ถ์ ๋ฐฉ๋ฒ์ ํตํ ํ๋ฅ ๋ถํฌ์ ์ถ์ 31
4.2 ์ฌํด ๊ฐ์คํ๋ฅ ์ฌ๊ท๊ฒฉํ 34
4.2.1 ๋ณตํฉ์ฌ์์ ์ด์ฉํ ์ฌํด ๋ถ์๊ณผ ์ฐ๊ตฌ๋ฐฐ๊ฒฝ 34
4.2.2 ์ฌํด์ ์์คํ
37
4.2.3 ๋ฐ์ํ๋ฅ 37
4.2.4 ๊ฐ์ค์น 38
4.2.5 ์ํ๋ ์ง์ (ฮฒ) 38
4.3 ์์๊ตฌ์กฐ๋ฅผ ๊ฐ๋ ์ฌ์์ ์ ์ฉ๊ณผ ๊ณ ์ฐฐ 39
4.3.1 ์ ์์ง ์ฐ๊ด์ง์ญ ์ํ๋ ํ๊ฐ์ ๊ฐ๋
๊ณผ ๋ฒ์ 40
4.3.2 ์ฌํด๋ณ ๋ฐ์ํ๋ฅ ์ฐ์ 46
4.3.3 ์ฌํด๋ณ ๊ฐ์ค์น ์ฐ์ 50
4.3.4 ์ ์ฉ ๊ฒฐ๊ณผ 54
4.4 ์๊ฒฐ 62
5 ๊ธฐํ๊ตฌ์กฐ๋ฅผ ๊ฐ๋ ๋ณตํฉํ๋ฅ ์ฌ์์ ํด์ 64
5.1 ๊ธฐํ๊ตฌ์กฐ ๋ฌธ์ ์ ํ๋ฅ ์์นํด์ 64
5.2 ํ์ฐ ๋ฐฉ์ ์๊ณผ ์ฐจ๋ถ 65
5.2.1 ํ์ฐ๋ฐฉ์ ์๊ณผ ์ ํ์ฐจ๋ถํด์ 65
5.2.2 ์ํจ์ ์ ํ์ฐจ๋ถํด์ ์ ์ ์ด์ 67
5.3 ํ๋ฅ ์ฌ๊ท๊ฒฉํ๋ฅผ ์ด์ฉํ ํ๋ฅ ์ ํ์ฐจ๋ถํด์ 68
5.4 ๊ธฐํ๊ตฌ์กฐ ๋ฌธ์ ์ ์ ์ฉ๊ณผ ๊ณ ์ฐฐ 69
5.4.1 ์ฌ๊ท๊ฒฉํ๋ฅผ ์ด์ฉํ ํ๋ฅ ์ ํ์ฐจ๋ถ๋ฒ์ ๊ฒ์ฆ 69
5.4.2 ๋ฐฐ์๊ฐ๋ฌธ ์ผํดํด์ 75
5.5 ์๊ฒฐ 88
6 ์ข
ํฉ๊ฒฐ๋ก 90
7 ์ฐธ๊ณ ์๋ฃ 92
Appendix 99
Abstract 104Docto