    Thermal Design and Performance of the Electrical Distribution Feed Box of the LHC prototype cell

    Get PDF
    The Electrical Distribution Feed Box (DFBS) is a 4.5 K saturated liquid helium cryostat constructed for the Large Hadron Collider (LHC) Prototype Cell (String 2). The thermal design of the DFBS is presented, with emphasis on the modelling of the cooling of the current lead chimneys via the helium bath boil-off gas and on the design of the lambda plate. The expected performance is compared to measurements done during the first operation phase of the LHC prototype cell

    First Results and Status of the LHC Test String 2

    Get PDF
    After the commissioning of String 2 Phase1 and the powering of the main circuits in autumn 2001, a short yet vigorous experimental program was carried-out to validate the final design choices for the technical systems of LHC. This program included the investigation of thermo-hydraulics of quenches quench propagation, power converter controls and tracking between power converters, as well as the measurement of currents induced in the beam screen after a quench and crossing the interconnects. Parameters significant for the LHC, such as heat loads, were also measured. During the winter shutdown the String was completed to a full cell with the addition of three pre-series dipoles (Phase 2). After a short description of the layout of Phase 1 and Phase 2, the results of the experiments are presented and the future experimental program is outlined

    The Preparation of the Cryomagnets and the Assembly of the LHC Test String 2

    Get PDF
    The numerous complex activities required to prepare the cryomagnets for the installation in String 2 are described. These include the configuration of the mechanical interfaces, thee conditioning of the beam tubes, the installation of beam screens and the instrumentation as well as the final checks. The preparation of the cryomagnets for String 2 has been a dress rehearsal for the preparation that the cryomagnets will undergo before their installation in the tunnel. After a description of the interconnection procedures of the components for String 2, the tests carried-out to release the String for operation are described. A brief account of the lessons learnt is also given