The robust single machine scheduling problem with uncertain release and processing times
In this work, we study the single machine scheduling problem with uncertain
release times and processing times of jobs. We adopt a robust scheduling
approach, in which the measure of robustness to be minimized for a given
sequence of jobs is the worst-case objective function value from the set of all
possible realizations of release and processing times. The objective function
value is the total flow time of all jobs. We discuss some important properties
of robust schedules for zero and non-zero release times, and illustrate the
added complexity in robust scheduling given non-zero release times. We propose
heuristics based on variable neighborhood search and iterated local search to
solve the problem and generate robust schedules. The algorithms are tested and
their solution performance is compared with optimal solutions or lower bounds
through numerical experiments based on synthetic data
Greed Works -- Online Algorithms For Unrelated Machine Stochastic Scheduling
This paper establishes performance guarantees for online algorithms that
schedule stochastic, nonpreemptive jobs on unrelated machines to minimize the
expected total weighted completion time. Prior work on unrelated machine
scheduling with stochastic jobs was restricted to the offline case, and
required linear or convex programming relaxations for the assignment of jobs to
machines. The algorithms introduced in this paper are purely combinatorial. The
performance bounds are of the same order of magnitude as those of earlier work,
and depend linearly on an upper bound on the squared coefficient of variation
of the jobs' processing times. Specifically for deterministic processing times,
without and with release times, the competitive ratios are 4 and 7.216,
respectively. As to the technical contribution, the paper shows how dual
fitting techniques can be used for stochastic and nonpreemptive scheduling
problems.Comment: Preliminary version appeared in IPCO 201
Minimizing value-at-risk in the single-machine total weighted tardiness problem
The vast majority of the machine scheduling literature focuses on deterministic
problems, in which all data is known with certainty a priori. This may be a reasonable assumption when the variability in the problem parameters is low. However, as variability in the parameters increases incorporating this uncertainty explicitly into a scheduling model is essential to mitigate the resulting adverse effects. In this paper, we consider the celebrated single-machine total weighted tardiness (TWT) problem in the presence of uncertain problem parameters. We impose a probabilistic constraint on the random TWT and introduce a risk-averse stochastic programming model. In particular, the objective of the proposed model is to find a non-preemptive static job processing sequence that minimizes the value-at-risk (VaR) measure on the random
TWT at a specified confidence level. Furthermore, we develop a lower bound on the optimal VaR that may also benefit alternate solution approaches in the future. In this study, we implement a tabu-search heuristic to obtain reasonably good feasible solutions and present results to demonstrate the effect of the risk parameter and the value of the proposed model with respect to a corresponding risk-neutral approach
Project scheduling under undertainty – survey and research potentials.
The vast majority of the research efforts in project scheduling assume complete information about the scheduling problem to be solved and a static deterministic environment within which the pre-computed baseline schedule will be executed. However, in the real world, project activities are subject to considerable uncertainty, that is gradually resolved during project execution. In this survey we review the fundamental approaches for scheduling under uncertainty: reactive scheduling, stochastic project scheduling, stochastic GERT network scheduling, fuzzy project scheduling, robust (proactive) scheduling and sensitivity analysis. We discuss the potentials of these approaches for scheduling projects under uncertainty.Management; Project management; Robustness; Scheduling; Stability;
- …