Expansion and Rehabilitation of the State Fish Pier in Gloucester, Massachusetts

Abstract

The State Fish Pier in Gloucester, Massachusetts, has been expanded and rehabilitated to provide an upgraded facility to support the local fishing industry. Expansion consisted of a new Finger Pier and solid fill extension of the existing pier. Rehabilitation consisted of replacing a deteriorated wharf with a new higher load carrying wharf. Subsurface conditions ranged from rock outcrops exposed at low tide at some locations to thick marine deposits overlying rock at other locations. Foundation support for the new Finger Pier and rehabilitated wharf consisted of concrete filled steel pipe piles, a portion of which had to he socketed into bedrock due to lack of soil overburden. Compression and tension load tests were performed to verify the pile design capacities