The Facility for Rare Isotope Beams (FRIB) Project has entered the phase of beam commissioning starting from the room-temperature front end and the superconducting linac segment of first 15 cryomodules. With the newly commissioned helium refrigeration system supplying 4.5K liquid helium to the quarter-wave resonators and solenoids, the FRIB accelerator team achieved the sectional key performance parameters as designed ahead of schedule accelerating heavy ion beams above 20MeV/u energy. Thus, FRIB accelerator becomes world's highest-energy heavy ion linear accelerator. We also validated machine protection and personnel protection systems that will be crucial to the next phase of commissioning. FRIB is on track towards a national user facility at the power frontier with a beam power two orders of magnitude higher than operating heavy-ion facilities. This paper summarizes the status of accelerator design, technology development, construction, commissioning as well as path to operations and upgrades