Series FACTS devices are capable of relieving congestion and reducing
generation costs in the power system. This paper proposes a planning model to
optimally allocate TCSCs in the transmission network considering the base case
and N−1 contingencies. We consider a single target year and select three
distinct load patterns to accommodate the yearly load profile. A reformulation
technique is utilized to linearize the nonlinear power flow constraint
introduced by a TCSC. Numerical case studies based on the IEEE 118-bus system
demonstrate the high performance of the proposed planning model.Comment: Preprint of DOI: 10.1109/NAPS.2016.7747948, North American Power
Symposium (NAPS), 201