Planiranje kapaciteta kod rezanja teških limova

Abstract

The present approach to capacity planning in operations producing heavy metal shapes causes problems in fulfilling the required financial and volume indexes in production, as well as in meeting the work order completion dates. The article represents the methodology for optimal production scheduling in operations producing heavy plate cut shapes, which significantly eliminates the above-mentioned problems. The methodology is based on the application Generalized Assignment Problem (GAP).Postojeći pristup planiranju kapaciteta u proizvodnji metalnih proizvoda od limova uzrokuje probleme kod ispunjavanja zahtjeva financijskih indeksa, razine produktivnosti te kompletiranja isporuke u danim rokovima. Članak daje metodologiju za optimiziranje terminiranja proizvodnje kod rezanja limova, koja značajno eliminira naprijed navedene probleme. Metodologija je temeljena na primjeni Općeg problema pridruživanja (OPP)