400 kW RF Stations Operational Experience : Overview of the operation experience during 2018-2019 with the Itelco-Electrosys and DB Science stations at the FREIA Laboratory

Abstract

We present the operational experience with the Itelco-Electrosys and DB Science 400 kW RF stations installed at the FREIA Laboratory. From the summer of 2018 to the summer of 2019 the stations were used for the test of the spoke cryomodule prototype for ESS. Unfortunately multiple issues with both RF stations delayed or inhibited normal operation. The Itelco-Electrosys station was out-of-operation from October 2018 to June 2019, due to multiple issues, which took a long time to understand and solve