An exact procedure for the resource-constrained weighted earliness-tardiness project scheduling problem.

Abstract

In this paper we study the resource-constrained project scheduling problem with weighted earliness-tardinesss penalty costs. Project activities are assumed to have a known deterministic due date, a unit earliness as well as a unit tardiness penalty cost and constant renewable resource requirements. The objective is to schedule the activities in order to minimize the total weighted earliness-tardinesss penalty cost of the project subject to the finish-start precedence constraints and the constant renewable resource availability constraints. With these features the problem becomes highly attractive in just-in-time environments.resource-constrained project scheduling; weighted earliness-tardiness costs; branch-and-bound; discounted cash flows; bound procedure;