Beam Commissioning Plan For LHC Collimation

Abstract

The Large Hadron Collider extends the present state-of-the-art in stored beam energy by 2-3 orders of magnitude. A sophisticated system of collimators is implemented along the 27 km ring and mainly in two dedicated cleaning insertions, to intercept and absorb unavoidable beam losses which could induce quenches in the superconducting (sc) magnets. 88 collimators for the two beams are initially installed for the so called Phase 1. An optimized strategy for the commissioning of this considerable number of collimators has been defined. This optimized strategy maximizes cleaning efficiency and tolerances available for operation, while minimizing the required beam time for collimator setup and ensuring at all times the required passive machine protection. It is shown that operational tolerances from collimation can initially be significantly relaxed