Commissioning Status of the CTF3 Delay Loop

Abstract

The CLIC Test Facility CTF3, built at CERN by an international collaboration, aims at demonstrating the linear collider by 2010. In particular, one of the main goals is to study the generation of high-current electron pulses by interleaving bunch trains in delay lines and rings using transverse RF deflectors. This will be done in the 42 m long delay loop, built under the responsibility of INFN/LNF, and the 84 m long combiner ring that will follow it. The delay loop installation was completed and its commissioning started at the end of 2005. In this paper the commissioning results are presented, including the first tests of beam recombination