A model for the cost of doing a cost estimate

Abstract

A model for estimating the cost required to do a cost estimate for Deep Space Network (DSN) projects that range from 0.1to0.1 to 100 million is presented. The cost of the cost estimate in thousands of dollars, C(sub E), is found to be approximately given by C(sub E) = K((C(sub p))(sup 0.35)) where C(sub p) is the cost of the project being estimated in millions of dollars and K is a constant depending on the accuracy of the estimate. For an order-of-magnitude estimate, K = 24; for a budget estimate, K = 60; and for a definitive estimate, K = 115. That is, for a specific project, the cost of doing a budget estimate is about 2.5 times as much as that for an order-of-magnitude estimate, and a definitive estimate costs about twice as much as a budget estimate. Use of this model should help provide the level of resources required for doing cost estimates and, as a result, provide insights towards more accurate estimates with less potential for cost overruns