Crystal Growth Furnace (CGF)

Abstract

The contract baseline, contract requirements review, contract modifications, contract problem areas and conclusions are addressed. Contract baseline was established 11 June 1987 and updated 1 December 1989. Significant changes were introduced into the 1989 baseline as compared to the original baseline. Contract modifications were made to add requirements as the program matured and as definition of requirements were completed. Problems were solved in real time through the contractor/customer team involvement and relationship to assure a timely and successful mission. The conclusion is that the CGF performed as designed and the experiments performed during the USML-1 Mission supports the conclusion