Construction progress of the cooling & ventilation in the LHC project

Abstract

After the LEP dismantling Phase the Cooling and Ventilation Group has started the LHC construction work. Year 2001 through to 2004 will certainly be the most important period of activity for the CV group in the erection phase The author will report on the current works that are in progress on the different LHC Points distinguishing between the Ventilation and the Water Cooling installations. The Ventilation work completed in the new surface buildings in Points 1, 4,5,6 and 8. The work for the Cooling plants comprehend to the pumping stations, the cooling towers and the chilled water production stations in Points 1 and 5, For all of these activities, an updated report of the progress the work, the planning and of the expenses are given. Finally, a brief overview of the future activities is presented

    Similar works

    Full text

    thumbnail-image

    Available Versions