Duration quantification and opportunities for improvement in the Texas Department of Transportation's utility relocation process

Abstract

Reducing the duration from planning to delivery of major highway projects is a major goal of the Texas Department of Transportation. A key component of this is the quantification of duration of the Utility Relocation process. This study quantified durations of historical utility relocation projects to provide guidelines in estimating future utility relocation project durations, modeled the TxDOT utility relocation process, and compiled key lessons learned for transportation project planners to better understand and improve efficiency in utility relocationsCivil, Architectural, and Environmental Engineerin