Abstract

The Proton Improvement Plan-II (PIP-II, [1]) linac will include 35 Single Spoke Resonators type 2 (SSR2). A total of eight pre-production SSR2 jacketed cavities will be procured and five installed in the first pre-production cryomodule. The mechanical design of the jacketed cavity has been finalized and it will be presented in this paper along with fabrication and processing experience. The importance of interfaces, quality controls and procurement aspects in the design phase will be remarked as well as lessons learned during the fabrication process. Furthermore, development studies will be presented together with other design validation tests

    Similar works

    Full text

    thumbnail-image

    Available Versions

    Last time updated on 31/10/2022