Foamed Asphalt Shoulders City of Muscatine, HR-529, 1993
Authors
Publication date
1 February 1993
Publisher
Abstract
Foamed asphalt shoulders were placed on an Industrial Connector road at
the south edge of Muscatine. The foamed asphalt was produced by injecting
1 to 2 percent water into hot asphalt cement in a patented foaming
chamber. A foam develops which is 10 to 15 times the original volume. of
the asphalt cement. A 3/8" limestone aggregate was used in the foamed
asphalt mixture. This foamed asphalt was placed on the shoulders and in
the radii on the Industrial Connector road in May 1987. The radii were
later replaced due to reconstruction, but the shoulders remain and
performed fairly well with some recent stripping and potholing. The
performance appeared to be lower than expected from conventional hot mix
on projects with similar traffic