509 research outputs found

    Generation of the transport service offer with application to timetable planning considering constraints due to maintenance work

    Get PDF
    Line planning is an important step in strategic timetable planning in public transport. In this step the transport offer for the customer is generated by the public transport operator, whereby the resulting costs for the operator should be as deep as possible. Mathematical models for line planning allow to create optimized line plans quickly. Planners can use these models to rate and select different alternatives. This is particularly valuable under the aspect of increasing maintenance and construction tasks of the railway infrastructure. We show, that in this case, it is possible to create functional requirements for automated timetable creation from the result of line planning step. The practical use of the involved models is illustrated by a real application example

    Satisfiability and Optimization in Periodic Traffic Flow Problems

    Get PDF
    Automatically calculating periodic timetables in public railway transport systems is an NP-complete problem – namely the Periodic Event Scheduling Problem (PESP). The original model is restricted to basic periodic timetabling. Extending the model by decisional transport networks with flows induces new possibilities in the timetabling and planning process. Subsequently, the given flexibility results in a generic model extension of PESP that can be applied in subsets of the timetabling process. The successful utilization of this approach is presented for distinct chain paths, duplicated chain paths and non-connected flow graphs that represent integration of routing and timetabling, planning of periodic rail freight train paths and track allocation, respectively. Furthermore, the encoding of this generic model into a binary propositional formula is introduced and the appropriate usage of several techniques like SAT solving and MaxSAT to calculate and optimize the corresponding instances will be presented accordingly. Computational results for real-world scenarios suggest the practical impact and give promising perspectives for further scientific research

    Opportunities and challenges with new railway planning approach in Sweden

    Get PDF
    Long lead times in railway planning can give rise to a significant discrepancy between the original plan and the traffic eventually operated, resulting in inefficient utilization of capacity. Research shows that the railway sector in Sweden would benefit from a different planning approach in which capacity consuming decisions are pushed forward in time whenever possible. This approach is currently being implemented at Trafikverket, the Swedish Transport Administration. With it follows a number of mathematical opportunities and challenges, some of which will be presented in this paper

    Improvement of maintenance timetable stability based on iteratively assigning event flexibility in FPESP

    Get PDF
    In the operational management of railway networks, an important requirement is the fast adaptation of timetable scenarios, in which operational disruptions or time windows with temporary unavailability of infrastructure, for instance during maintenance time windows, are taken into consideration. In those situations, easy and fast reconfiguration and recalculation of timetable data is of central importance. This local and temporal rescheduling results in shifted departure and arrival times and sometimes even in modified stop patterns at intermediate stations of train runs. In order to generate reliable timetabling results it is a prerequisite that train-track assignments, as well as operational and commercial dependencies are taken into consideration. In order to refer to the right level of detail for modelling track infrastructure and train dynamics in the computer aided planning process we present a generic model that we call Track-Choice FPESP (TCFPESP), as it implements suitable extensions of the established PESP-model. We show, how the service intention (the data structure for timetable specification) together with resource capacity information entered into a standard timetabling tool like Viriato can be utilized in order to configure the TCFPESP model. In addition, we are able to calculate quantitative performance measures for assessing timetable quality aspects. In order to achieve this we present a method for evaluating travel times based on passenger routings and a method for evaluating timetable robustness based on max-plus algebra. This approach supports the planner to generate integrated periodic timetable solutions in iterative development cycles and taking into account intervals for local maintenance work

    Development of a prototype for the automated generation of timetable scenarios specified by the transport service intention

    Get PDF
    Within the next 5 to 10 years, public transport in Switzerland as well as in other European countries will experience major technological and organisational changes. However, changes will also take place on the customer side, resulting in different mobility behaviour and demand patterns. These changes will lead to additional challenges for transport service providers in private as well as public domains. Time to market will be a key success factor and it is unnecessary to mention that due to these factors the speed and flexibility of business processes in freight as well as in passenger transport industry have to be increased significantly. Within the railway value chain (line planning, timetabling and vehicle scheduling etc.) the coordination of the individual planning steps is a key success factor. SBB as the leading service provider in public transport in Switzerland has recognized this challenge and, together with various partners, initiated the strategic project Smart Rail 4.0. The ZHAW and especially the Institute for Data Analysis and Process Design (IDP) of the School of Engineering wants to be part of this transformation process and to contribute with research and educational activities. The IDP research therefore aims for the transformation of academic and scientific know-how to practical applicability. In a first step this concerns directly the current Smart Rail 4.0 TMS-PAS project activities, that concentrate on timetabling issues. The IDP project team considers the integration of the line planning and the timetabling process as crucial for practical applications. To address this in the current research project, we present an application concept that enables the integration of these two major process steps in the transport service value-chain. Although it turns out from our research, that the technical requirements for the integration of the process can be satisfied, rules and conditions for a closer cooperation of the involved business units, the train operating companies and the infrastructure operating company, have to be improved and to be worked out in more detail. In addition to a detailed application concept with use cases for the timetabling process we propose a methodology for computer aided timetable generation based on the central planning object known as ‘service intention’. The service intention can be used to iteratively develop the timetable relying on a ‘progressive feasibility assessment’, a feature that is requested in practice. Our proposed model is based on the ‘track-choice’ and line rotation extension of the commonly known method for the generation of periodic event schedules ‘PESP’. The extension makes use of the track infrastructure representation which is also used in the line planning and timetabling system Viriato. This system that is widely used by public transport planners and operators. With the help of Viriato, it is rather easy to configure the timetabling problem in sufficient detail. On the other side, the level of detail of the considered data is light enough to algorithmically solve practical timetabling problems of realistic sizes. Taking into consideration the technical and operational constraints given by rolling stock, station and track topology data on one hand, and the commercial requirements defined by a given line concept on the other, the method presented generates periodic timetables including train-track assignments. In the first step, the standardized data structure ‘service intention’ represents the line concept consisting of train paths and frequencies. Due to the utilization of infrastructure-based track capacities, we are also able to assess the feasibility of the line concept given. Additionally, the method allows for handling temporary resource restrictions (e.g. caused by construction sites or operational disturbances). In order to assess the performance of the resulting timetable we present a framework for performance measurement that addresses the customer convenience (in terms of start-to-end travel time) as well as operational stability requirements (in terms of delay sensitivity and critical relations)

    On the delivery robustness of train timetables with respect to production replanning possibilities

    Get PDF
    Measuring timetable robustness is a complex task. Previous efforts have mainly been focused on simulation studies or measurements of time supplements. However, these measurements don't capture the production flexibility of a timetable, which is essential for measuring the robustness with regard to the trains' commercial activity commitments, and also for merging the goals of robustness and efficiency. In this article we differentiate between production timetables and delivery timetables. A production timetable contains all stops, meetings and switch crossings, while a delivery timetable only contains stops for commercial activities. If a production timetable is constructed such that it can easily be replanned to cope with delays without breaking any commercial activity commitments it provides delivery robustness without compromising travel efficiency. Changing meeting locations is one of the replanning tools available during operation, and this paper presents a new framework for heuristically optimising a given production timetable with regard to the number of alternative meeting locations. Mixed integer programming is used to find two delivery feasible production solutions, one early and one late. The area between the two solutions represents alternative meeting locations and therefore also the replanning enabled robustness. A case study from Sweden demonstrates how the method can be used to develop better production timetables

    A MILP model for quasi-periodic strategic train timetabling

    Get PDF
    In railways, the long-term strategic planning is the process of evaluating improvements to the railway network (e.g., upgrading a single track line to a double track line) and changes to the composition/frequency of train services (e.g., adding 1 train per hour along a certain route). The effects of different combinations of infrastructure upgrades and updated train services (also called scenarios), are usually evaluated by creating new feasible timetables followed by extensive simulation. Strategic Train Timetabling (STT) is indeed the task of producing new tentative timetables for these what-if scenarios. Unlike the more classic train timetabling, STT can often overlook (or at least give less importance to) some complementary aspects, such as crew and rolling stock scheduling. On the other hand, the different scenarios are likely to lead to very different timetables, hindering the common and effective practice of using existing timetables to warm start the solution process. We introduce the concept of quasi-periodic timetables, that are timetables where certain subsets of trains need to start at almost (rather than precisely) the same minute of every period. The additional flexibility offered by quasi-periodic timetables turned out to be crucial in real-life scenarios characterized by elevated train traffic. We describe a MILP based approach for strategic quasi-periodic train timetabling and we test it on 4 different realistic what-if scenarios for an important line in Norway. The timetables produced by our algorithm were ultimately used by the Norwegian Railway Directorate to select 3 out of the 4 scenarios for phasing the progressive expansion of the JȪren line.publishedVersio

    State of the Art Overview on Automatic Railway Timetable Generation and Optimization

    Get PDF
    In railway transportation, each train needs to have a timetable that specifies which track at which time will be occupied by it. This task can be addressed by automatization techniques both in generating a timetable and in optimizing an existing one. In this paper, we give an overview on the state of the art of these techniques. We study the computation of a technically valid slot for a train that guarantees a (short) spatial and temporal way through the network. Furthermore, the construction of a cyclic timetable where trains operate e.g. every 60 minutes, and the simultaneous construction of timetables for multiple trains are considered in this paper. Finally, timetables also need to be robust against minor delays. We will review the state of the art in the literature for these aspects of railway timetabling with respect to models, solution algorithms, complexity results and applications in practice

    The new Dutch timetable: The OR revolution

    Get PDF
    In December 2006, Netherlands Railways introduced a completely new timetable. Its objective was to facilitate the growth of passenger and freight transport on a highly utilized railway network, and improve the robustness of the timetable resulting in less train delays in the operation. Further adjusting the existing timetable constructed in 1970 was not option anymore, because further growth would then require significant investments in the rail infrastructure. Constructing a railway timetable from scratch for about 5,500 daily trains was a complex problem. To support this process, we generated several timetables using sophisticated operations research techniques, and finally selected and implemented one of these timetables. Furthermore, because rolling-stock and crew costs are principal components of the cost of a passenger railway operator, we used innovative operations research tools to devise efficient schedules for these two resources. The new resource schedules and the increased number of passengers resulted in an additional annual profit of 40 million euros (60million)ofwhichabout10millioneuroswerecreatedbyadditionalrevenues.Weexpectthistoincreaseto70millioneuros(60 million) of which about 10 million euros were created by additional revenues. We expect this to increase to 70 million euros (105 million) annually in the coming years. However, the benefits of the new timetable for the Dutch society as a whole are much greater: more trains are transporting more passengers on the same railway infrastructure, and these trains are arriving and departing on schedule more than they ever have in the past. In addition, the rail transport system will be able to handle future transportation demand growth and thus allow cities to remain accessible. Therefore, people can switch from car transport to rail transport, which will reduce the emission of greenhouse gases.
    corecore