Permutation Flowshop Scheduling with Earliness and Tardiness Penalties
We address the permutation flowshop scheduling problem with earliness and tardiness penalties (E/T) and common due date of jobs. Large number of process and discrete parts industries follow flowshop type of production process. There are very few results reported for multi-machine E/T scheduling problems. We show that the problem can be sub-divided into three groups- one, where the due date is such that all jobs are necessarily tardy; the second, where the due date is such that it is not tight enough to act as a constraint on scheduling decision; and the third is a group of problems where the due date is in between the above two. We develop analytical results and heuristics for problems arising in each of these three classes. Computational results of the heuristics are reported. Most of the problems in this research are addressed for the first time in the literature. For problems with existing heuristics, the heuristic solution is found to perform better than the existing results.
Common Due-Date Problem: Exact Polynomial Algorithms for a Given Job Sequence
This paper considers the problem of scheduling jobs on single and parallel
machines where all the jobs possess different processing times but a common due
date. There is a penalty involved with each job if it is processed earlier or
later than the due date. The objective of the problem is to find the assignment
of jobs to machines, the processing sequence of jobs and the time at which they
are processed, which minimizes the total penalty incurred due to tardiness or
earliness of the jobs. This work presents exact polynomial algorithms for
optimizing a given job sequence or single and parallel machines with the
run-time complexities of and respectively, where
is the number of jobs and the number of machines. The algorithms take a
sequence consisting of all the jobs as input and
distribute the jobs to machines (for ) along with their best completion
times so as to get the least possible total penalty for this sequence. We prove
the optimality for the single machine case and the runtime complexities of
both. Henceforth, we present the results for the benchmark instances and
compare with previous work for single and parallel machine cases, up to
jobs.Comment: 15th International Symposium on Symbolic and Numeric Algorithms for
Scientific Computin
Greedy randomized dispatching heuristics for the single machine scheduling problem with quadratic earliness and tardiness penalties
In this paper, we present greedy randomized dispatching heuristics for the single machine scheduling problem with quadratic earliness and tardiness costs, and no machine idle time. The several heuristic versions differ, on the one hand, on the strategies involved in the construction of the greedy randomized schedules. On the other hand, these versions also differ on whether they employ only a final improvement step, or perform a local search after each greedy randomized construction. The proposed heuristics were compared with existing procedures, as well as with optimum solutions for some instance sizes. The computational results show that the proposed procedures clearly outperform their underlying dispatching heuristic, and the best of these procedures provide results that are quite close to the optimum. The best of the proposed algorithms is the new recommended heuristic for large instances, as well as a suitable alternative to the best existing procedure for the larger of the middle size instances.scheduling, single machine, early/tardy, quadratic penalties, greedy randomized dispatching rules
A Novel Approach to the Common Due-Date Problem on Single and Parallel Machines
This paper presents a novel idea for the general case of the Common Due-Date
(CDD) scheduling problem. The problem is about scheduling a certain number of
jobs on a single or parallel machines where all the jobs possess different
processing times but a common due-date. The objective of the problem is to
minimize the total penalty incurred due to earliness or tardiness of the job
completions. This work presents exact polynomial algorithms for optimizing a
given job sequence for single and identical parallel machines with the run-time
complexities of for both cases, where is the number of jobs.
Besides, we show that our approach for the parallel machine case is also
suitable for non-identical parallel machines. We prove the optimality for the
single machine case and the runtime complexities of both. Henceforth, we extend
our approach to one particular dynamic case of the CDD and conclude the chapter
with our results for the benchmark instances provided in the OR-library.Comment: Book Chapter 22 page
Dynamic resource constrained multi-project scheduling problem with weighted earliness/tardiness costs
In this study, a conceptual framework is given for the dynamic multi-project scheduling problem with weighted earliness/tardiness costs (DRCMPSPWET) and a mathematical programming formulation of the problem is provided. In DRCMPSPWET, a project arrives on top of an existing project portfolio and a due date has to be quoted for the new project while minimizing the costs of schedule changes. The objective function consists of the weighted earliness tardiness costs of the activities of the existing projects in the current baseline schedule plus a term that increases linearly with the anticipated completion time of the new project. An iterated local search based approach is developed for large instances of this problem. In order to analyze the performance and behavior of the proposed method, a new multi-project data set is created by controlling the total number of activities, the due date tightness, the due date range, the number of resource types, and the completion time factor in an instance. A series of computational experiments are carried out to test the performance of the local search approach. Exact solutions are provided for the small instances. The results indicate that the local search heuristic performs well in terms of both solution quality and solution time
Minimizing weighted total earliness, total tardiness and setup costs
The paper considers a (static) portfolio system that satisfies adding-up contraints and the gross substitution theorem. The paper shows the relationship of the two conditions to the weak dominant diagonal property of the matrix of interest rate elasticities. This enables to investigate the impact of simultaneous changes in interest rates on the asset demands.
- …