59,519 research outputs found
Truthful Online Scheduling with Commitments
We study online mechanisms for preemptive scheduling with deadlines, with the
goal of maximizing the total value of completed jobs. This problem is
fundamental to deadline-aware cloud scheduling, but there are strong lower
bounds even for the algorithmic problem without incentive constraints. However,
these lower bounds can be circumvented under the natural assumption of deadline
slackness, i.e., that there is a guaranteed lower bound on the ratio
between a job's size and the time window in which it can be executed.
In this paper, we construct a truthful scheduling mechanism with a constant
competitive ratio, given slackness . Furthermore, we show that if is
large enough then we can construct a mechanism that also satisfies a commitment
property: it can be determined whether or not a job will finish, and the
requisite payment if so, well in advance of each job's deadline. This is
notable because, in practice, users with strict deadlines may find it
unacceptable to discover only very close to their deadline that their job has
been rejected
Scheduling policies and system software architectures for mixed-criticality computing
Mixed-criticality model of computation is being increasingly
adopted in timing-sensitive systems. The model not only
ensures that the most critical tasks in a system never fails,
but also aims for better systems resource utilization in normal condition. In this report, we describe the widely used
mixed-criticality task model and fixed-priority scheduling
algorithms for the model in uniprocessors. Because of the
necessity by the mixed-criticality task model and scheduling
policies, isolation, both temporal and spatial, among tasks is
one of the main requirements from the system design point
of view. Different virtualization techniques have been used
to design system software architecture with the goal of isolation. We discuss such a few system software architectures
which are being and can be used for mixed-criticality model
of computation
Multi-project scheduling with 2-stage decomposition
A non-preemptive, zero time lag multi-project scheduling problem with multiple modes and limited renewable and nonrenewable resources is considered. A 2-stage decomposition approach is adopted to formulate the problem as a hierarchy of 0-1 mathematical programming models. At stage one, each project is reduced to a macro-activity with macro-modes resulting in a single project network where the objective is the maximization of the net present value and the cash flows are positive. For setting the time horizon three different methods are developed and tested. A genetic algorithm approach is designed for this problem, which is also employed to generate a starting solution for the exact solution procedure. Using the starting times and the resource profiles obtained in stage one each project is scheduled at stage two for minimum makespan. The result of the first stage is subjected to a post-processing procedure to distribute the remaining resource capacities. Three new test problem sets are generated with 81, 84 and 27 problems each and three different configurations of solution procedures are tested
A Lazy Bailout Approach for Dual-Criticality Systems on Uniprocessor Platforms
© 2019 by the authors. Licensee MDPI, Basel, Switzerland.A challenge in the design of cyber-physical systems is to integrate the scheduling of tasks of different criticality, while still providing service guarantees for the higher critical tasks in case of resource-shortages caused by faults. While standard real-time scheduling is agnostic to the criticality of tasks, the scheduling of tasks with different criticalities is called mixed-criticality scheduling. In this paper we present the Lazy Bailout Protocol (LBP), a mixed-criticality scheduling method where low-criticality jobs overrunning their time budget cannot threaten the timeliness of high-criticality jobs while at the same time the method tries to complete as many low-criticality jobs as possible. The key principle of LBP is instead of immediately abandoning low-criticality jobs when a high-criticality job overruns its optimistic WCET estimate, to put them in a low-priority queue for later execution. To compare mixed-criticality scheduling methods we introduce a formal quality criterion for mixed-criticality scheduling, which, above all else, compares schedulability of high-criticality jobs and only afterwards the schedulability of low-criticality jobs. Based on this criterion we prove that LBP behaves better than the original {\em Bailout Protocol} (BP). We show that LBP can be further improved by slack time exploitation and by gain time collection at runtime, resulting in LBPSG. We also show that these improvements of LBP perform better than the analogous improvements based on BP.Peer reviewedFinal Published versio
- …