416 research outputs found

    Research Trends and Outlooks in Assembly Line Balancing Problems

    Get PDF
    This paper presents the findings from the survey of articles published on the assembly line balancing problems (ALBPs) during 2014-2018. Before proceeding a comprehensive literature review, the ineffectiveness of the previous ALBP classification structures is discussed and a new classification scheme based on the layout configurations of assembly lines is subsequently proposed. The research trend in each layout of assembly lines is highlighted through the graphical presentations. The challenges in the ALBPs are also pinpointed as a technical guideline for future research works

    Mathematical model and agent based solution approach for the simultaneous balancing and sequencing of mixed-model parallel two-sided assembly lines

    Get PDF
    Copyright © 2014 Elsevier. NOTICE: this is the author’s version of a work that was accepted for publication in International Journal of Production Economics. Changes resulting from the publishing process, such as peer review, editing, corrections, structural formatting, and other quality control mechanisms may not be reflected in this document. Changes may have been made to this work since it was submitted for publication. A definitive version was subsequently published in International Journal of Production Economics, DOI: 10.1016/j.ijpe.2014.08.010One of the key factors of a successfully implemented mixed-model line system is considering model sequencing problem as well as the line balancing problem. In the literature, there are many studies, which consider these two tightly interrelated problems individually. However, we integrate the model sequencing problem in the line balancing procedure to obtain a more efficient solution for the problem of Simultaneous Balancing and Sequencing of Mixed-Model Parallel Two-Sided Assembly Lines. A mathematical model is developed to present the problem and a novel agent based ant colony optimisation approach is proposed as the solution method. Different agents interact with each other to find a near optimal solution for the problem. Each ant selects a random behaviour from a predefined list of heuristics and builds a solution using this behaviour as a local search rule along with the pheromone value. Different cycle times are allowed for different two-sided lines located in parallel to each other and this yields a complex problem where different production cycles need to be considered to build a feasible solution. The performance of the proposed approach is tested through a set of test cases. Experimental results indicate that considering model sequencing problem with the line balancing problem together helps minimise line length and total number of required workstations. Also, it is found that the proposed approach outperforms other three heuristics tested

    Simultaneous balancing and sequencing of mixed-model parallel two-sided assembly lines

    Get PDF
    Copyright © 2014 Taylor & Francis. This is an Accepted Manuscript of an article published by Taylor & Francis in International Journal of Production Research on 31 January 2014, available online: http://www.tandfonline.com/10.1080/00207543.2013.879618Growing interests from customers in customised products and increasing competitions among peers necessitate companies to configure their manufacturing systems more effectively than ever before. We propose a new assembly line system configuration for companies that need intelligent solutions to satisfy customised demands on time with existing resources. A mixed-model parallel two-sided assembly line system is introduced based on the parallel two-sided assembly line system previously proposed by Ozcan et al. (Balancing parallel two-sided assembly lines, International Journal of Production Research, 48 (16), 4767-4784, 2010). The mixed-model parallel two-sided assembly line balancing problem is illustrated with examples from the perspective of simultaneous balancing and sequencing. An agent based ant colony optimisation algorithm is proposed to solve the problem. This algorithm is the first attempt in the literature to solve an assembly line balancing problem with an agent based ant colony optimisation approach. The algorithm is illustrated with an example and its operational procedures and principles explained and discussed

    Balancing of parallel U-shaped assembly lines

    Get PDF
    Copyright © 2015 Elsevier. This is a PDF file of an unedited manuscript that has been accepted for publication in Computers & Operations Research (doi: 10.1016/j.cor.2015.05.014). As a service to our customers we are providing this early version of the manuscript. The manuscript will undergo copyediting, typesetting, and review of the resulting galley proof before it is published in its final citable form. Please note that during the production process errors may be discovered which could affect the content, and all legal disclaimers that apply to the journal pertain. Please cite this article as: Ibrahim Kucukkoc, David Z. Zhang, Balancing of parallel U-shaped assembly Lines, Computers & Operations Research, http://dx.doi.org/10.1016/j.cor.2015.05.014A new hybrid assembly line design, called Parallel U-shaped Assembly Line system, is introduced and characterised along with numerical examples for the first time. Different from existing studies on U-shaped lines, we combine the advantages of two individual line configurations (namely parallel lines and U-shaped lines) and create an opportunity for assigning tasks to multi-line workstations located in between two adjacent U-shaped lines with the aim of maximising resource utilisation. Utilisation of crossover workstations, in which tasks from opposite areas of a same U-shaped line can be performed, is also one of the main advantages of the U-shaped lines. As in traditional U-shaped line configurations, the newly proposed line configuration also supports the utilisation of crossover workstations. An efficient heuristic algorithm is developed to find well-balanced solutions for the proposed line configurations. Test cases derived from existing studies and modified in accordance with the proposed system in this study are solved using the proposed heuristic algorithm. The comparison of results obtained when the lines are balanced independently and when the lines are balanced together (in parallel to each other) clearly indicates that the parallelisation of U-shaped lines helps decrease the need for workforce significantly.Balikesir UniversityTurkish Council of Higher Educatio

    Balancing of mixed-model parallel U-shaped assembly lines considering model sequences

    Get PDF
    This is the author accepted manuscript. The final version is available from Taylor & Francis via the DOI in this record.As a consequence of increasing interests in customised products, mixed-model lines have become the most significant components of today’s manufacturing systems to meet surging consumer demand. Also, U-shaped assembly lines have been shown as the intelligent way of producing homogeneous products in large quantities by reducing the workforce need thanks to the crossover workstations. As an innovative idea, we address the mixed-model parallel U-shaped assembly line design which combines the flexibility of mixed-model lines with the efficiency of U-shaped lines and parallel lines. The multi-line stations utilised in between two adjacent lines provide extra efficiency with the opportunity of assigning tasks into workstations in different combinations. The new line configuration is defined and characterised in details and its advantages are explained. A heuristic solution approach is proposed for solving the problem. The proposed approach considers the model sequences on the lines and seeks efficient balancing solutions for their different combinations. An explanatory example is also provided to show the sophisticated structure of the studied problem and explain the running mechanism of the proposed approach. The results of the experimental tests and their statistical analysis indicated that the proposed line design requires fewer number of workstations in comparison with independently balanced mixed-model U-lines

    Balancing and Sequencing of Mixed Model Assembly Lines

    Get PDF
    Assembly lines are cost efficient production systems that mass produce identical products. Due to customer demand, manufacturers use mixed model assembly lines to produce customized products that are not identical. To stay efficient, management decisions for the line such as number of workers and assembly task assignment to stations need to be optimized to increase throughput and decrease cost. In each station, the work to be done depends on the exact product configuration, and is not consistent across all products. In this dissertation, a mixed model line balancing integer program (IP) that considers parallel workers, zoning, task assignment, and ergonomic constraints with the objective of minimizing the number of workers is proposed. Upon observing the limitation of the IP, a Constraint Programming (CP) model that is based on CPLEX CP Optimizer is developed to solve larger assembly line balancing problems. Data from an automotive OEM are used to assess the performance of both the MIP and CP models. Using the OEM data, we show that the CP model outperforms the IP model for bigger problems. A sensitivity analysis is done to assess the cost of enforcing some of the constraint on the computation complexity and the amount of violations to these constraints once they are disabled. Results show that some of the constraints are helpful in reducing the computation time. Specifically, the assignment constraints in which decision variables are fixed or bounded result in a smaller search space. Finally, since the line balance for mixed model is based on task duration averages, we propose a mixed model sequencing model that minimize the number of overload situation that might occur due to variability in tasks times by providing an optimal production sequence. We consider the skip-policy to manage overload situations and allow interactions between stations via workers swimming. An IP model formulation is proposed and a GRASP solution heuristic is developed to solve the problem. Data from the literature are used to assess the performance of the developed heuristic and to show the benefit of swimming in reducing work overload situations

    Modelling and Solving Mixed-model Parallel Two-sided Assembly Line Problems

    Get PDF
    The global competitive environment and the growing demand for personalised products have increased the interest of companies in producing similar product models on the same assembly line. Companies are forced to make significant structural changes to rapidly respond to diversified demands and convert their existing single-model lines into mixed-model lines in order to avoid unnecessary new line construction cost for each new product model. Mixed-model assembly lines play a key role in increasing productivity without compromising quality for manufacturing enterprises. The literature is extensive on assembling small-sized products in an intermixed sequence and assembling large-sized products in large volumes on single-model lines. However, a mixed-model parallel two-sided line system, where two or more similar products or similar models of a large-sized product are assembled on each of the parallel two-sided lines in an intermixed sequence, has not been of interest to academia so far. Moreover, taking model sequencing problem into consideration on a mixed-model parallel two-sided line system is a novel research topic in this domain. Within this context, the problem of simultaneous balancing and sequencing of mixed-model parallel two-sided lines is defined and described using illustrative examples for the first time in the literature. The mathematical model of the problem is also developed to exhibit the main characteristics of the problem and to explore the logic underlying the algorithms developed. The benefits of utilising multi-line stations between two adjacent lines are discussed and numerical examples are provided. An agent-based ant colony optimisation algorithm (called ABACO) is developed to obtain a generic solution that conforms to any model sequence and it is enhanced step-by-step to increase the quality of the solutions obtained. Then, the algorithm is modified with the integration of a model sequencing procedure (where the modified version is called ABACO/S) to balance lines by tracking the product model changes on each workstation in a complex production environment where each of the parallel lines may a have different cycle time. Finally, a genetic algorithm based model sequencing mechanism is integrated to the algorithm to increase the robustness of the obtained solutions. Computational tests are performed using test cases to observe the performances of the developed algorithms. Statistical tests are conducted through obtained results and test results establish that balancing mixed-model parallel two-sided lines together has a significant effect on the sought performance measures (a weighted summation of line length and the number of workstations) in comparison with balancing those lines separately. Another important finding of the research is that considering model sequencing problem along with the line balancing problem helps algorithm find better line balances with better performance measures. The results also indicate that the developed ABACO and ABACO/S algorithms outperform other test heuristics commonly used in the literature in solving various line balancing problems; and integrating a genetic algorithm based model sequencing mechanism into ABACO/S helps the algorithm find better solutions with less amount of computational effort

    Using response surface design to determine the optimal parameters of genetic algorithm and a case study

    Get PDF
    Copyright © 2013 Taylor & Francis. This is an Accepted Manuscript of an article published by Taylor & Francis in International Journal of Production Research on 09 June 2013, available online: http://www.tandfonline.com/10.1080/00207543.2013.784411Genetic algorithms are efficient stochastic search techniques for approximating optimal solutions within complex search spaces and used widely to solve NP hard problems. This algorithm includes a number of parameters whose different levels affect the performance of the algorithm strictly. The general approach to determine the appropriate parameter combination of genetic algorithm depends on too many trials of different combinations and the best one of the combinations that produces good results is selected for the program that would be used for problem solving. A few researchers studied on parameter optimisation of genetic algorithm. In this paper, response surface depended parameter optimisation is proposed to determine the optimal parameters of genetic algorithm. Results are tested for benchmark problems that is most common in mixed-model assembly line balancing problems of type-I (MMALBP-I)

    Mixed-model parallel two-sided assembly line balancing problem: A flexible agent-based ant colony optimization approach

    Get PDF
    This is the author accepted manuscript. The final version is available from the publisher via the DOI in this record.Assembly lines are frequently used as a production method to assemble complex products. Two-sided assembly lines are utilized to assemble large-sized products (e.g., cars, buses, trucks). Locating two lines in parallel helps improve line efficiency by enabling collaboration between the line workers. This paper proposes a mixed-model parallel two-sided assembly line system that can be utilized to produce large-sized items in an inter-mixed sequence. The mixed-model parallel two-sided line balancing problem is defined and the advantages of utilizing multi-line stations across the lines are discussed. A flexible agent-based ant colony optimization algorithm is developed to solve the problem and a numerical example is given to explain the method systematically. The proposed algorithm builds flexible balancing solutions suitable for any model sequence launched. The dynamically changing workloads of workstations (based on specific product models during the production process) are also explored. A comprehensive experimental study is conducted and the results are statistically analyzed using the well-known paired sample t-test. The test results indicate that the mixed-model parallel two-sided assembly line system reduces the workforce need in comparison with separately balanced mixed-model two-sided lines. It is also shown that the proposed algorithm outperforms the tabu search algorithm and six heuristics often used in the assembly line balancing domain
    • …
    corecore