A two-level genetic algorithm for the multi-mode resource-constrained project scheduling problem
This paper presents a genetic algorithm for the multimode
resource-constrained project scheduling problem (MRCPSP),
in which multiple execution modes are available for each of the
activities of the project. The objective function is the minimization of
the construction project completion time. To solve the problem, is
applied a two-level genetic algorithm, which makes use of two
separate levels and extend the parameterized schedule generation
scheme by introducing an improvement procedure. It is evaluated the
quality of the schedule and present detailed comparative
computational results for the MRCPSP, which reveal that this
approach is a competitive algorithm
Towards Merging Binary Integer Programming Techniques with Genetic Algorithms
This paper presents a framework based on merging a binary integer programming technique with a genetic algorithm. The framework uses both lower and upper bounds to make the employed mathematical formulation of a problem as tight as possible. For problems whose optimal solutions cannot be obtained, precision is traded with speed through substituting the integrality constrains in a binary integer program with a penalty. In this way, instead of constraining a variable u with binary restriction, u is considered as real number between 0 and 1, with the penalty of Mu(1-u), in which M is a large number. Values not near to the boundary extremes of 0 and 1 make the component of Mu(1-u) large and are expected to be avoided implicitly. The nonbinary values are then converted to priorities, and a genetic algorithm can use these priorities to fill its initial pool for producing feasible solutions. The presented framework can be applied to many combinatorial optimization problems. Here, a procedure based on this framework has been applied to a scheduling problem, and the results of computational experiments have been discussed, emphasizing the knowledge generated and inefficiencies to be circumvented with this framework in future
Recommended from our members
An adaptive memory programming framework for the resource-constrained project scheduling problem
The Resource-Constrained Project Scheduling Problem (RCPSP) is one of the most intractable combinatorial optimisation problems that combines a set of constraints and objectives met in a vast variety of applications and industries. Its solution raises major theoretical challenges due to its complexity, yet presenting numerous practical dimensions. Adaptive memory programming (AMP) is one of the most successful frameworks for solving hard combinatorial optimisation problems (e.g. vehicle routing and scheduling). Its success stems from the use of learning mechanisms that capture favourable solution elements found in high-quality solutions. This paper challenges the efficiency of AMP for solving the RCPSP, to our knowledge, for the first time in the literature. Computational experiments on well-known benchmark RCPSP instances show that the proposed AMP consistently produces high-quality solutions in reasonable computational times
Mode-Based versus Activity-Based Search for a Nonredundant Resolution of the Multimode Resource-Constrained Project Scheduling Problem
[EN] This paper addresses an energy-based extension of the Multimode Resource-Constrained Project Scheduling Problem (MRCPSP) called MRCPSP-ENERGY. This extension considers the energy consumption as an additional resource that leads to different execution modes (and durations) of the activities. Consequently, different schedules can be obtained. The objective is to maximize the efficiency of the project, which takes into account the minimization of both makespan and energy consumption. This is a well-known NP-hard problem, such that the application of metaheuristic techniques is necessary to address real-size problems in a reasonable time. This paper shows that the Activity List representation, commonly used in metaheuristics, can lead to obtaining many redundant solutions, that is, solutions that have different representations but are in fact the same. This is a serious disadvantage for a search procedure. We propose a genetic algorithm(GA) for solving the MRCPSP-ENERGY, trying to avoid redundant solutions by focusing the search on the execution modes, by using the Mode List representation. The proposed GA is evaluated on different instances of the PSPLIB-ENERGY library and compared to the results obtained by both exact methods and approximate methods reported in the literature. This library is an extension of the well-known PSPLIB library, which contains MRCPSP-ENERGY test cases.This paper has been partially supported by the Spanish Research Projects TIN2013-46511-C2-1-P and TIN2016-80856-R.Morillo-Torres, D.; Barber, F.; Salido, MA. (2017). Mode-Based versus Activity-Based Search for a Nonredundant Resolution of the Multimode Resource-Constrained Project Scheduling Problem. Mathematical Problems in Engineering. 2017:1-15. https://doi.org/10.1155/2017/4627856S1152017Mouzon, G., Yildirim, M. B., & Twomey, J. (2007). Operational methods for minimization of energy consumption of manufacturing equipment. International Journal of Production Research, 45(18-19), 4247-4271. doi:10.1080/00207540701450013Hartmann, S., & Sprecher, A. (1996). A note on «hierarchical models for multi-project planning and scheduling». European Journal of Operational Research, 94(2), 377-383. doi:10.1016/0377-2217(95)00158-1Christofides, N., Alvarez-Valdes, R., & Tamarit, J. M. (1987). Project scheduling with resource constraints: A branch and bound approach. European Journal of Operational Research, 29(3), 262-273. doi:10.1016/0377-2217(87)90240-2Zhu, G., Bard, J. F., & Yu, G. (2006). A Branch-and-Cut Procedure for the Multimode Resource-Constrained Project-Scheduling Problem. INFORMS Journal on Computing, 18(3), 377-390. doi:10.1287/ijoc.1040.0121Kolisch, R., & Hartmann, S. (1999). Heuristic Algorithms for the Resource-Constrained Project Scheduling Problem: Classification and Computational Analysis. International Series in Operations Research & Management Science, 147-178. doi:10.1007/978-1-4615-5533-9_7Józefowska, J., Mika, M., Różycki, R., Waligóra, G., & Węglarz, J. (2001). Annals of Operations Research, 102(1/4), 137-155. doi:10.1023/a:1010954031930Bouleimen, K., & Lecocq, H. (2003). A new efficient simulated annealing algorithm for the resource-constrained project scheduling problem and its multiple mode version. European Journal of Operational Research, 149(2), 268-281. doi:10.1016/s0377-2217(02)00761-0Alcaraz, J., Maroto, C., & Ruiz, R. (2003). Solving the Multi-Mode Resource-Constrained Project Scheduling Problem with genetic algorithms. Journal of the Operational Research Society, 54(6), 614-626. doi:10.1057/palgrave.jors.2601563Zhang, H., Tam, C. M., & Li, H. (2006). Multimode Project Scheduling Based on Particle Swarm Optimization. Computer-Aided Civil and Infrastructure Engineering, 21(2), 93-103. doi:10.1111/j.1467-8667.2005.00420.xJarboui, B., Damak, N., Siarry, P., & Rebai, A. (2008). A combinatorial particle swarm optimization for solving multi-mode resource-constrained project scheduling problems. Applied Mathematics and Computation, 195(1), 299-308. doi:10.1016/j.amc.2007.04.096Li, H., & Zhang, H. (2013). Ant colony optimization-based multi-mode scheduling under renewable and nonrenewable resource constraints. Automation in Construction, 35, 431-438. doi:10.1016/j.autcon.2013.05.030Lova, A., Tormos, P., Cervantes, M., & Barber, F. (2009). An efficient hybrid genetic algorithm for scheduling projects with resource constraints and multiple execution modes. International Journal of Production Economics, 117(2), 302-316. doi:10.1016/j.ijpe.2008.11.002Peteghem, V. V., & Vanhoucke, M. (2010). A genetic algorithm for the preemptive and non-preemptive multi-mode resource-constrained project scheduling problem. European Journal of Operational Research, 201(2), 409-418. doi:10.1016/j.ejor.2009.03.034Węglarz, J., Józefowska, J., Mika, M., & Waligóra, G. (2011). Project scheduling with finite or infinite number of activity processing modes – A survey. European Journal of Operational Research, 208(3), 177-205. doi:10.1016/j.ejor.2010.03.037Kolisch, R., & Hartmann, S. (2006). Experimental investigation of heuristics for resource-constrained project scheduling: An update. European Journal of Operational Research, 174(1), 23-37. doi:10.1016/j.ejor.2005.01.065Debels, D., De Reyck, B., Leus, R., & Vanhoucke, M. (2006). A hybrid scatter search/electromagnetism meta-heuristic for project scheduling. European Journal of Operational Research, 169(2), 638-653. doi:10.1016/j.ejor.2004.08.020Paraskevopoulos, D. C., Tarantilis, C. D., & Ioannou, G. (2012). Solving project scheduling problems with resource constraints via an event list-based evolutionary algorithm. Expert Systems with Applications, 39(4), 3983-3994. doi:10.1016/j.eswa.2011.09.062Drexl, A. (1991). Scheduling of Project Networks by Job Assignment. Management Science, 37(12), 1590-1602. doi:10.1287/mnsc.37.12.1590BOCTOR, F. F. (1996). Resource-constrained project scheduling by simulated annealing. International Journal of Production Research, 34(8), 2335-2351. doi:10.1080/0020754960890502
Recommended from our members
Project schedule optimisation utilising genetic algorithms
This thesis was submitted for the degree of Doctor of Philosophy and awarded by Brunel University.This thesis extends the body of research into the application of Genetic Algorithms to the Project Scheduling Problem (PSP). A thorough literature review is conducted in this area as well as in the application of other similar meta-heuristics. The review extends previous similar reviews to include PSP utilizing the Design Structure Matrix (DSM), as well as incorporating recent developments.
There is a need within industry for optimisation algorithms that can assist in the identification of optimal schedules when presented with a network that can present a number of possible alternatives. The optimisation requirement may be subtle only performing slight resource levelling or more profound by selecting an optimal mode of execution for a number of activities or evaluating a number of alternative strategies.
This research proposes a unique, efficient algorithm using adaptation based on the fitness improvement over successive generations. The algorithm is tested initially using a MATLAB based implementation to solve instances of the travelling salesman problem (TSP). The algorithm is then further developed both within MATLAB and Microsoft Project Visual Basic to optimise both known versions of the Resource Constrained Project Scheduling Problems as well as investigating newly defined variants of the problem class
Recommended from our members
Discrete flower pollination algorithm for resource constrained project scheduling problem
YesIn this paper, a new population-based and nature-inspired metaheuristic algorithm, Discrete Flower Pollination Algorithm (DFPA), is presented to solve the Resource Constrained Project Scheduling Problem (RCPSP). The DFPA is a modification of existing Flower Pollination Algorithm adapted for solving combinatorial optimization problems by changing some of the algorithm's core concepts, such as flower, global pollination, Lévy flight, local pollination. The proposed DFPA is then tested on sets of benchmark instances and its performance is compared against other existing metaheuristic algorithms. The numerical results have shown that the proposed algorithm is efficient and outperforms several other popular metaheuristic algorithms, both in terms of quality of the results and execution time. Being discrete, the proposed algorithm can be used to solve any other combinatorial optimization problems.Innovate UKAwarded 'Best paper of the Month
Insertion Algorithms with Justification for Solving the Resource-Constrained Project Scheduling
The paper presents the resource-constrained project scheduling problem with the makespan minimisation criterion. To solve the problem, the authors propose insertion algorithms which generate schedules with use of forward serial and parallel decoding procedures. Schedules are improved with the use of the double justification by extremes technique (first right and then left justification). The efficiency of the procedures proposed is tested on standard test problems from the PSPLIB library
- …