Optimalisasi Waktu Dan Biaya Proyek Dengan Analisa Crash Program
Optimization of time and cost is effort to use short time with minimum cost for reaching a job with good results and profits while still concern with quality of project. Crash Program analysis using addition of working hours, is intended to decrease working hours but it is still keeping the productivity number. The direct cost of the project will increase with the addition of working hours, but inversely proportional to the indirect cost of the project. Therefore, the purpose of this final project is to get optimization point between time and cost of the project, in order to get minimum cost to shorten project implementation time. Crash Program is one of scheduling method to shorten project implemention time. By using this program, earned critical path of a project to decide an acitivity that the implementation time can be shortened